A Special Meeting of the City Council of the City of Bremerton was called for a Tour of Public Works &
Utilities Projects and Facilities. The tour began in the Upper Parking Lot of the NORM DICKS
GOVERNMENT CENTER, 345 6' Street, Bremerton, Washington, Wednesday, June 25, from 9:00 AM to
3:30 PM; and members of the public were provided an opportunity to participate. Council Members
present were Mike Sullivan, Leslie Daugs, Jerry McDonald, and Dino Davis.
The Itinerary was as follows:
9:00 a.m. Met in Norm Dicks Government Center, Upper Parking Lot
9:06 a.m. Sewer Lift Station EB3 (observed beach sewer locations; point out
last year's Manette LID project enroute)
9:12 a.m. Enroute to Reservoirs 17 and 20, Ridge Lane. Trenton to 11 to Perry (TBD
Overlay). Up Perry to Cascade Trail (TBD Slurry Sea[) back to Trenton (TBD
Overlay Cascade Trail to Holman) to Sylvan to Petersville (limits of Water
Utility) to Riddell past Pine to Vena and also discuss EB -9
9:30 a.m. Reservoirs 17 and 20, Ridge Lane
9:40 a.m. Enroute to East Side Treatment Plant via Central Valley Road / Tracyton / Lebo
(discuss Tracyton sewer issues; vactor need); and stop at Pat Carey Vista to
discuss seismic valves
9:55 a.m. East Side Treatment Plant (key facility for CSO program; demonstrate backup
power)
10:15 a.m. Enroute to Boardwalk commercial facilities via Manette Bridge (discuss LWW /
Washington Avenue projects / Manette Bridge ADA and $80 million investment
— roundabout architectural entrance to Manette)
10:23 a.m. Ferry employee entrance: tour Boardwalk commercial facilities (tunnel backup
power — demonstrate; tour grease interceptor; dumpsters)
10:43 a.m. Enroute to 11` /Ford via Burwell /Callow /Kitsap Way /Adele. discuss Tunnel at
Park; Warren Avenue traffic island; Burwell bulbouts; signals and signal
coordination
10:53 a.m. Sewer Manhole at 11 and Summit: discussion of old infrastructure and safety
demonstration. Work zone setup; vactor on site. Observe depth /construction
of manhole harness use
11:15 a.m. WB -3 (Shipyard pump station)
11:33 a.m. Enroute to Casad Dam (discuss Gorst sewer; water infrastructure)
11:50 a.m. Casad Dam (discuss watershed access and control)
12:05 p.m. Enroute to headworks facility (discuss water infrastructure)
12:10 p.m. Headworks facility (discuss surface water source vs groundwater)
12:20 p.m. Enroute to Advanced Disinfection Facility (lunch)
12:25 p.m. Advanced Disinfection (Ultraviolet) Facility (discuss wells)
i
City Council Special Meeting Minutes (PW Tour)
Wednesday, June 25, 2014
9:00 AM to 3:30 PM
Page 2 of 2
1:05 p.m. Enroute to Anderson Creek production wells; drive through biosolids facilities
near Golf Course (discuss biosolids application)
1:25 p.m. Anderson Creek production wells
1:40 p.m. Enroute to Reservoir 4 via Anderson Hill Road (swing into Bayside
Development; point out water service area; discuss intertie with Port Orchard
water system
1:55 p.m. Reservoir 4 and Water System Corrosion Control Facility
2:10 p.m. Enroute to West Side Sewer Treatment Plant
2:15 p.m. West Side Sewer Treatment Plant
2:45 p.m. Enroute to Oyster Bay Facility
2:50 p.m. Oyster Bay main complex (yard space south side; demonstrate backup power;
inside tour; plan going forward for Engineering)
3:10 p.m. Depart for Norm Dicks Government Center
3:25 p.m. Arrive at Norm Dicks Government Center, Upper Parking Lot
With no further business, the Special Meeting ended at 3:30 PM.
Prepared and Submitted by:
L RI SMITH
Legislative Assistant
Attest:
SHANNON CORIN, City Clerk
GREG EELER, City Council President
GW:SC. cg