CITY OF BREMERTON
CITY COUNCIL
SUBJECT. Pacific Avenue — 6` to 11` Study Session Date June 12, 2013
Streets Project — Installation of Electric COUNCIL MEETING Date June 19, 2013
Vehicle Charging Stations Department Public Works
Presenter Martin
Phone 5758
SUMMARY- With the new bids on the Pacific Avenue project, the issue of how /whether to include
the charging stations is ready to be decided In the research conducted at Council's request, a key
constraint emerged ECOtality, the company which operates the stations provided by the
Department of Commerce grant, controls the fee structure Our analysis indicates that at $2 00 per
hour, these stations can make money for the City, but at $1 00 per hour (the fee ECOtality insists
on), the stations lose money ECOtality has held out the possibility that fees could be increased in
the future, but will not commit to a $2 00 fee for Bremerton yet Given this constraint, the
Administration proposes the following
1) All infrastructure to support charging stations be installed, as currently provided in the Pacific
Avenue reconstruction contract This will result in the ability to install four charging stations
2) For now, install only two of the charging stations at this location Pursue other locations to install
the remaining two stations
3) Install the other two charging stations at locations to be determined, if arrangements satisfactory
to the Council can be developed
ATTACHMENTS:
1 Staff Report
2 Financial analysis w/ $1 /hour fee and $2 /hour fee
FISCAL IMPACTS (Include Budgeted Amount) At $1 00 /hour fee, each station will lose about
$1,425 per year on average over 5 years If the fee is $2 00 /hour, the two stations likely still lose
money initially but can pay for themselves as usage increases
STUDY SESSION AGENDA ❑ No Presentation ® Full Presentation
STUDY SESSION ACTION. ❑ Consent Agenda ® General Business ❑ Public Hearing
RECOMMENDED MOTION
i
Move to install the base infrastructure for four charging stations in accordance with the Pacific
Avenue Reconstruction Project documents Installation of charging stations for this location to be
considered at a later date and is subject to Council approval
COUNCIL ACTION: ❑ Approve �eny ❑ Table ❑ Continue ❑ No Action
Form Updated 01/25/13