HomeMy WebLinkAbout5156 Contract Number: 5156
Vendor: STAN PALMER CONSTRUCTION, INC.
Subject: Low Impact Development Projects
Department: Engineering
File Class: LEG 12 -1
Begin Date: 8/6/2012
End Date:
Review Date:
Vault Date:
Comments: CO #1 6/3/13
CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO 1
PROJECT NAME Low Impact Development Projects
824, 828, 4492,
PROJECT NO 5363 CONTRACTOR Stan Palmer Construction
ORIGINAL CONTRACT AMOUNT $827,245 01 DAYS 90
PREVIOUSLY APPROVED CHANGES $0 00 DAYS
THIS CHANGE $24,736 57 DAYS 1
REVISED CONTRACT AMOUNT $851,98158 DAYS 91
This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order Items The
increase or decrease in contract price shown below includes any applicable taxes
DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT
CONTRACT CONTRACT TIME
AMOUNT AMOUNT EXTENSION
°' °—' ($) ($) (DAYS)
o: o:
1 Force Account — LID Pacific
X 11 Cap - off side sewer after installing 8x6 wye 13929
X 12 Repair water service line hit at the service corp.
while digging side sewer lateral at wrongly marked
location. 40454
Taxes $404.54 x 8.6% 3479
X 13 Additional time for digging of sewer lateral that was
wrongly marked. 49931
X 14 Repair water service line broken while digging
because it was wrongly marked. 10401
Taxes $104.01 x 8.6% 894
X 15 Additional time for digging of sewer lateral that was
wrongly marked. 99825
X 16 Tie back for watermam at Pacific and 12th. 2,08123
Taxes $2,081.23 x 8.6% 17899
X 17 Installation of yard drain at 1104 Pacific. 18500
X 1.8 Installation of sewer lateral to avoid conflict with
existing storm sewer. 56853
X 19 Fix broken sewer forcemam. 47241
X 110 Remove underground water tank. 15137
X 1 11 Connect roof drain to planter bed. 13900
CONTRACT CHANGE ORDER NO
PROJECT NAME Low Impact Development Projects
X 2 Force Account —LID E 11th
21 Fill pothole with cold mix, 11/29/12 3866
22 Fill trench with cold mix, 11/27/12 1,43878
23 Fill potholes with cold mix, 11 /19/12 9362
24. Remove concrete communication duct 52338
25 Fill pothole with cold mix, 11 /02/12 9362
26 Fill pothole with cold mix, 11/01/12 30651
X 3 Replace concrete pavement In poor condition that collapsed
during the installation of the sanitary sewer.
531.3 sy x $38/sy 20,189 40
X 4 Replace sanitary manhole at Pacific Avenue and Sheldon
Blvd. 2,98260 1
X 5 Grind pavement at intersection of Pitt Ave and E II' St and
haul -out grindings. 29592
X 6 Placed asphalt behind sidewalk to have transition between
sidewalk and parking area at the SE corner of Pitt Ave and E
11' St. 3,65669
7 Overall change in contract amount based on the difference
between the total increase on some bid items and the total
decrease on some bid items. 1 (10,848 27)
NET CHANGE IN CONTRACT AMOUNT 35,584.84 (10,848.27) 1
INCREASE OR (DECREASE)
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or
nature ansing from or connected with any work either covered or affected by this Change Order, including, without
Iimitabon, claims related to contract time, on -site or home office overhead, or lost profits Nothing in this Change Order
shall limit the City's right to bring a claim for past performance
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price
specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in
work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order
This document will become a supplement of the contract and all provisions will apply hereto It is understood that this
Change Order shall be effective when approved by the City of Bremerton
Page 2 of 3
CONTRACT CHANGE ORDER NO
PROJECT NAME. Low Impact Development Projects
The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on
the parties of this contract In addition, Contractor warrants that it has or will inform the surety of this change, and shall
take appropriate action to modify any bonds required under the contract to address this change
RECOMMENDED �0,� -
/13
PROJECT ENGIN ER Date
RECOMMENDED S 3 3
CITY ENGINEER / DIRECTOR OF PUBLIC WORKS Date
ACCEPTED
CON Date
APPROVED ' �3
MAYOR Date
APPROVED AS TO FORM: ATTE
BhOnerton City Attorney City Clerk
Page 3 of 3
Contract Number
Vendor•
Sub�ect.
Department.
File Class
Begin Date
End Date•
Review Date
Vault Date•
5156
STAN PALMER CONSTRUCTION, INC.
Low Impact Development Pro�ects
Engineering
LEG 12-1
8/6/2012
Comments .
CONTI2ACT
CITY OF BREMERTON, KITSAP COUNTY, WASHINGTON
TH1S AGREEMENT, made and entered mto th�s 6th day of August , 2p12 ,
between the C�ty of Bremerton under and by virtue of Title 35 RCW (cit�es) as amended, and
Stan Palmer Construction Inc.
here�nafter called the Contractor
WITIVESSETH
That �n cons�derat�on of the terms and cond�t�ons contained herein and attached and made
a part of th�s agreement, the parties hereto covenant and agree as foliows
1 The Contractor shall do all work and furnish all tools, materials and equipment for the
Low Impact Development Pro�ects, �n accordance wrth and as descnbed in the attached Plans
and Specificat�ons, and the 2012 Standard Specificat�ons of the Washington State Department of
Transportation wh�ch are by this reference tncorporated here�n and made part hereof and shall
perform any changes m the work in accord with the Contract Documents
The Contractor shail piovide and bear the expense of all eqwpment, work, and labor, of any sort
whatsoever that may be required for the transfer of materials and for constructmg and complet�ng
the work prov�ded for m these Contract Documents except those �tems mentioned there�n to be
furn►shed by the C�ty of Bremerton
II The Gty of Bremerton hereby contracts with Contractor and Contractor hereby agrees
to provide the matena(s and to do and cause to be done the above descnbed work and to complete
and fin�sh the same in accord with the attached Plans and Spec�fications and the tenns and
conditions herem contamed and hereby Contracts to pay for the same according to the attached
spec�fications and the schedule of umt or itemized prices at the time and m the manner and upon
the condrt�ons prov�ded for in this Contract
III The Contractor �s and shall be at all t►mes actmg as an �ndependent contractor and
not as an employee of the C�ty The Contractor shali secure at its expense, and shall be
respons�ble for all payments of mcome tax, soctai secur�ty, state mdustrial tnsurance
compensation, unemployment compensation, and all other payroll deductions for the Contractor,
officer, agents, employees and sub-contractors The Contractor shall also secure all applicable
business I�censes, �f required, �n connectton wrth the contract serv�ces, including all required
(icenses for Contractor's officers, agents, employees and subcontractors
IV The Contractor for himself/herself, and for his/her heirs, executors, admm�strators,
successors, assigns, does hereby agree to the full performance of all the covenants herein
contained upon the part of the Contractor
V lt is further provided that no Itab�lity shali attach to the C�ty of Bremerton by reason
of entenng into this Contract, except as provided herem
Crry of Brernerton
Low lmpact Development Pro�ects
Water and Sa»rlary Sewer Replacements LD-9 June 2012
VI INDEMNIFICATION Contractor sha(I defend, mdemn�fy and hold the Gt��, its
officers, officials, employees, agents and volunteers harmless from any and all claims, ui�uries,
damages, losses or surts includmg all legal cost and attorney fees, ar�s�ng aut of or in connection
�vith the performance of this agreement, eacept foi �nJunes and damages solely caused by the
Cuy's negligence
The City's inspect�on or acceptance of any of Contractor's work when completed shall not be
grounds to avoid any ofthese covenants of mdemnification
Should a court of competent�ur�sd�ct�on determ�ne that this agreement is sub�ect to RCW
4 24 115, then, m the event of I�abil�ry for damages aris�ng out of bodily in�ury to persons or
damages to property caused by or result�ng from the concurrent negt�gence of the Contractor
and the Ciry, its officials, employees, agents and volunteers, the Contractor's I�ab�l�ty
hereunder shall be only to the extent of the Contractor's negtigence
IT IS FURTHER SPECIEICALLY AND EXPRESSLY UNDERSTOOD THAT THIS
INDEMNIFICATION CONSITUTES TEIE CONTRACTOR'S WAIVER OF 1MMUN[TY
UNDER iNDUSTRIAL INSURANCE TITLE 51 RCW, SOLELY FOR THE PURPOSE OF
THIS 1NDEMNIFICATION THE PARTIES ACKNOWLEDGE THAT THEY HAVE
MUTUALLY NEGOTIATED THIS WANER
The prov�sions of this secUon shall surv�ve the expnaUon of term�nation of this agreement
IN WITNESS WHEREOF, the Cotrtractor has erecuted th�s instrument, on the day and year first
below written and the Local Agency Approving Author�ty has caused this �nstrument to be executed
by and in the name of sa�d Gty of Bremerton the day and year tirst above written
Executed by the Contractor this 6th day of August � 2012
T om Abplanalp, Sr. Vice Preside
Contractor
E�cecuted by the Local Agency this �T� ay of .TGGC► , 201/�
�
/!'t O/'�..
City of B merton Approv�ng Authority
(SEAL) �
C�ty a/�6remerlon
LaN� lmpact Detielopment Pro�ects
Water and San��ary Sewer Replacemenls
City of Bremerton Atto y
L D-l0
J�me 2012
Proposal
To The City of Bremerton City Clerk
345 6�' Street, Swte 600
Bremertoq Washu�►gton 98337
lfiis cerhfies that the unders�gned has exammed the location of
Low Impact Development Pro�ects
City of Bremerton Nos 824, 828, 5311
In the Crty of Bremerton
And that the Plans, Specifications, and Conhact govermng the work embraced m th�s unprovement, and the
method by wluch payment wdl be made for said work, is understood The undersigned hereby proposes to
undertake and complete the work embraced m tlus unprovement, or as much thereof as can be completed wrth
the money available m accordance with the sa�d Plans, Specificabons, and Contract, and the followmg schedule
of rates and pnces
(Note Unit pnces for all �tems, all extensions and total amount of bid must be shown All entries must be typed or
entered m u�k )
C�ty ofBremerton
Low lmpact Development Pro�ects
Water and San�tary Sewer Replacements LD-2
June 2011
LOW IMPACT OEVELOPAAENT PRWECTS - SCHEDULE A BID FORM
PACIFIC AVENUE 11TH STREET T0137H STREET
�,6�U c�
Page 4
Provided to Builders Exchange of WA, Inc For usage Conditions Agreement see www bxwa com - Always Venfy Scale
SUBTOTAL (RULE 171) ta2 g p� 5b
SCHEdULE A TOTAL a (,� � � � �i7,50
LOW IMPACT DEVELOPMEk7 PRQJECT5 • 5CHEDULE B B1D FORM
E 11TH 8TREET SHORE DRtVE TO PI7TAVENl1E
Page 5
Provided to Budders F�cchange of WA, Inc For usage Conditions Agreement see www bxwa com - Always Venfy Scale
SUBTOTAL (RULE 1i1) 9' q1 C�
SCHEDULE B TOTAL q�
LUW IMPACT DEVELQPMENT PROJECTS - SCHEDULE C BID FORM
WATER MAIN REPLACEMENT
1TEM REF TO
NO SPEC DESCRIPT'ION OF ITEM
C I 1-09 S M INOR CHANGES
C2 1-09 7 MOBILIZATION (PACIFiC)
C3 1-09 7 MOBILIZATION (E 11TI-I�
C4 1-10 5 PR0IECT TEMPORARY TRAFFIC CONTROL (PAC[FIC)
CS I-10.5 PROIECT TEMPORARY TRAFFIC CONTROL (E 1 ITH)
C6 5-05 5 TRENCH RESTORATION
C7 7-09.5 CONTRQGLED DENSI7Y FILL
C8 7-09 5 RESTRAiNED ]OINT DI PIPE FOR WATER MAIN 12 IN DIA (PACIFIC�
C9 7-09 5 RESTRAINED JOINT DI PiPE FOR WATER MAIN 12 IN D[A E 11T
CI O 7-09 5 RESTRAlNED JOtNT DUCTILE IRON PIPE FOR WATER MAIN 8 Ild D[A
Ct 1 7-09 5 RESTRAIAlED JOINT DUCTILE IRQN PIPE FOR WATER MAIN G M DIA
C12 7-09 5 REMOVAL AND REPLACEMENT OF UNSUITABLE MATERIAL
C13 7-09 5 BANK RUN GRAVEL FOR TRENCH BACiCFiLL (PACIFIC)
Ci4 7-09 5 BANK RUN GRAVEL FOR TRENCH BACKFILL E 11TH
C 15 7-09 5 SHORING OR EXTRA EXCAVATION TRENCH (PACIFIC)
C15 7-09 5 SHORING OR EXTRA EXCAVATIQN TREAICH (E 11T1�
C17 7-12.5 GA7'E VALVE 12 IN (PACIFIC)
C18 7-12 5 GATE VALVE 12 M E I 1
Cl9 7-12 S GATE VALVE 8 IN
C20 7-14 5 HYDRANT ASSEMBLY
C21 7-15 5 SERVICE RECONNECTION
C22 7-I5.5 SERVICE CONNECT[ON 21N DIAM
C23 7-IS 5 SERVICE CONNECTION 1 1N DIAM (PACIFIC)
C24 '7-15 5 SERVICE CONNECTION 1 1N DIAM (E ! 1THl
SUBTQTAL (RULE 170)
SALES TAX (8 6%)
SCHEDULE C TOTAL
1 F�fty peroent ottotal mobif�zahon cost
2 Twenty five perc�nt of total mobtl¢adon cost
3 Flfty peroent of total temporary tr�c control cost
4 Twenty five per�nt of totaf temparary traffic cantroi cost
ANTITY � UNIT I UNIT PRICE l AMOUNT
i LS. $1.00 $1 C
t �.s. 5 po0 0 5 660�
� �.s � 5 nr�, o0
� �-S L5 0 l .�.
i L.S � 5 p0U . o b 15 o0U 0
56 C Y 5 5 O 3 0�SO pd
50 C Y 5 � 0 0 ? 5 �0 pa
350 L F. in0 n D 3S. nr�1 .��
50
l0U
100
1,901
I .bUl
2
3
3
2
12
i
4
3
L.F (� p0 3o d�
L.F 5 0 D 500 �
�-F 5 g a 3��( c
CY o7 �b I �50
C Y o� 3 Q
cY. 3a o 3 a
S F. po 1 60
S.F Q I (.p 00.
EACH �?rlil n� 4 r� n�
EACH
EACH
EACH
EACH
� �� �
1• ►• :1�
� �• - ! �
� �� O� O O 1�- � �
`o
1(�a,a$s.�o �
_[3. �1S(n 5( �
-��`� � �
�
0
a�
m
c
N
s
U
�
�
N
�
�
m
0
m
��
a� >
�o
m
aa
LOW IMPACT DEVELOPMENT PROJECTS - SCHEDULE D BID FORM
SEWER REPLACEMENT
ITEM REF TO EST
NO SPEC DESCEZIPTiON OF ITEM QUANTITY UNIT UNIT PRICE AMOUNT
D I 1-09 6 M1NOR CHANGES 1 L S $1.00 $1 UO
D2 1-09 7 MOBILIZATION 1 L S D p60 QO ( 0 6�
D3 1-10 5 PROJECT TEMPORARY TRAFFIC CONTROL 1 L S 31` Oa �c� 3`f bdv �
D4 5-OS 5 TRENCH RESTOR.ATION 54 C Y 5 5 0 0 a q�o � o
D7 7-OS 5 STRUCTURE EXCAVATION CLASS B 385 C Y 5.(� - 7 5 Od
D8 7-17 5 PVC SANITARY SEWER 8-IN DtA PIPB 143 L.F 5 `7 �aa 6(�
D9 7-17 5 PVC SAluITARY SEWER 10-IN DIA P1PE 195 L F 5� 00 0 Ra0 pa
D10 7-17 5 TESTING SEWER P1PE 33$ L F. 3. p C� b/�{ p
Dl I 7-17 5 REMOVAL AND REPLACEMENT OF UNSUITABLE MATERIAL l00 C Y 5� 0� 5� 00 ov
D12 7-17 5 BAAIK RUN GRAVEL FOR TRENCH BACKFILL 120 C Y 3� 0� y Og0 00
D13 7-17 5 SHORING OR EXTRA EXCAVATION TRENCH 3,458 S F 6 U 3 Y5g 0�
D14 7-17 5 CONTROLLED DENSITY FILL 50 C.Y 150 00 7 SZ�� O�
D15 7-18 5 SIDE SEWER CONNECI"ION 14 EACH (p35 0 0 � �S O �a
D16 7-19 5 SEWER CLEANOUT 1 EACH 7�j O 00 �sd c�d
SUBTOTAL (TAX RULE l 71)
SCHEDULE D TOTAL
GRAND TOTAL
1 Fifty percent of total mobilizat�on cast
2 Twenty five percent of total rt�bil�zation cost
3 Fifiy percent of totai temporary traffic control cost
4 Twenty five percent of total temparary traffic control cost
I oa,7�o oa
t oa . ��s� �o�
� d7,a�5.0 t
U
C
Q
�
�
O
N
0I
C
N
L
U
X
ll.�
a
a�
�
�
m
0
v
��
��
�o m
aa
PROPOSAL — CONTINUED
The bidder �s hereby advised that by s�gning of this proposal he/she �s deemed to have acknowledged all
requuements and signed all certtficates herem
A proposal guaranty m an amount of five percent (5%) of the total b�d, based upon the approxunated
estunate of quantihes at the above pnces and in the form as mdtcated below, is attached hereto
Cash
Cashier's Check
Dollars ($
Certified Check
Dollars ($
Proposal Bond
In the amount of
) payable to the C�ty of Bremerton
, In the amount of
) payable to the City of Bremerton
Rece�pt is hereby acknowledged of (The Bidder hereby acknowledges receipt of addenda by uiitialmg
after each addendum received )
Addendum No 1 �
Addendum No 2
Addendum No 3
Signature of Autho ' � Official(s): -
-- �
Tom Abplanalp, Senior Vice-President
Firm Name
(Address)
State of Washmgton Contractor's License No
C�ty of Bremerton Business License No
Note
1
2
3
Federal ID No
Stan Palmer Construction, Inc
5108 SW Nixon Loop
Bremerton, WA 98312
ST-AN-PC*202NF
#12861
91-1078790
This proposal is not transferable and any alteration of the firm's name entered hereon without pnor
permission from the City of Bremerton w�ll be cause for considenng the proposal nonresponsive and
subsequent re�ection of the bid
Please refer to Secrion 1-02 6 of the Standard Spec�ficahons, re "Preparatton of Proposal "
Should it be necessary to modify th�s proposal erther ui wnt�ng or by electronic means, please make
reference to the following proposal name u� your commumcation Low Impact Development
Projects
Ctty of Bremerton
Low Impact Development Pro�ects
Water and Samtary Sewer Replacements LA4
June 2012
Failure to return this Declaration as part of the bid proposal
package will make the bid nonresponsive and ineligible for
award.
NON-COLLUSION DECLARATION
1, by signing the proposal, hereby declare, under
penalty of per�ury under the laws of the Un�ted
States that the foliowing statements are true and
correct
1 That the undersigned person(s), firm, assoaahon or
corporation has (have) not, either directly or mdirectly,
entered �nto any agreement, participated in any collusion,
or otherwise taken any action m restraint of free
competitwe bidding in connect�on with the pro�ect for which
this proposal is submitted
2 That by signing the signature page of this
proposal, I am deemed to have signed and to
have agreed to the provisions of this declaration
NOTICE TO ALL BIDDERS
To report riggmg activities call
1-800-424-9071
The U S Department of Transportation (USDOT) operates
the above toll-free "hotline" Monday through Friday,
8 OOa m to 5 OOp m, eastern time Anyone with
knowledge of possible bid rigging, bidder collusion, or
other fraudulent activities should use the "hotline" to report
such activities
The "hotline" is part of USDOT's continuing effort to identify and investigate
highway construction contract fraud and abuse and is operated under the
direction of the USDOT Inspector General All information wdl be treated
confidentially and caller anonymity wdl be respected
City of Bremerton
Low Impact Development Pro�ects
Water and Sanrtary Sewer Replacemenis LD-7
June 2012
` _ _ - ��.
� � ��
Executive Correspondence Routing Memo
Date: July 30, 2012
Description: Contract — Low Impact Development Pro�ects
Action Requested: Mayor's Signature
Originator: Ed Aban �
Please forward to City Clerk upon execution of documents. The City Clerk will forward the
Contractor's and Engineer's copies to the originator.
Coordination / Approval / Recommendation:
Public Works Manager:
Public Works Director:
Recommended
Recommended
Finance Director (if applicable): Recommended
City Attorney (if applicable): Recommended
Mayor: Approval / Signature
Initials/date
Initials/date
Initials/date
I n rtia a � ����\�
Publ�c Works & Utd�t�es I 100 Oyster Bay Ave N, Bremerton, WA 98312 * Phone (360) 473-5315 * Fax (360) 473-5018