HomeMy WebLinkAbout3176 RESOLUTION NO. 3176
A RESOLUTION of the City Council of the City of
Bremerton, Washington, adopting the 2013 — 2018 Six Year
Transportation Improvement Plan
WHEREAS, after proper notice, the City Council of the City of Bremerton held a
public hearing at the regular meeting of the City Council at 5 30 p in on July 18, 2012 to
consider public testimony on the City's proposed 2013 - 2018 Six Year Transportation
Improvement Plan and, having considered public testimony to the Plan and in accordance with
the provisions of RCW 47 80, NOW THEREFORE,
THE CITY COUNCIL OF THE CITY OF BREMERTON, WASHINGTON,
DOES HEREBY RESOLVE AS FOLLOWS
SECTION]. The 2013 through 2018 Six Year Transportation Improvement
Plan, set forth in Exhibit "A" attached hereto and herewith filed with the City Clerk, is hereby
adopted
SECTION 2. Severab&U If anyone or more sections, subsections, or
sentences of this Resolution are held to be unconstitutional or invalid, such decision shall not
affect the validity of the remaining portion of this Resolution and the same shall remain in full
force and effect
SECTION 3. Effective Date This Resolution shall take effect and be in force
immediately upon its passage
PASSED by the City Council of the City of Bremerton, Washington this o'
day of 3kA,, , 2012
AM MCDONALD, Council President
APPROVED AS TO FORM ATTEST
RObER A. LUBOVICH, City SHANNON CORIN, City Clerk
R \Legal\Legal\Resolutions \Public cs ?.008 Resolution for TIP doc
1 Six Year Transportation Plan
AWL
1 �,'„� Six Year Transportation Improvement Program bw
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 <
m A PIN /Project No B STIP ID 3 0 3 .o�.
C Project Title y eo eo q 0 1
c D Road Name or Number 0 9 a o ' r" E `
n o
m 0 Q E Begin 8, End Termini M 'a a z .� C .� S.
u °1 F Project Description G Structure ID m a o A H c.
14 WA -03928 11 O 0 010 CE No
11 Street Overcrossing Replacement
Eleventh Street
0 1 E of SR310 to 0 11 E of SR310
Replacement of existing structure 08522400
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2014 STP(U) 432,500 0 67,500 500,000
P CN 2015 STP(U) 2,595,000 0 405,000 3,000,000
Totals 3,027,500 0 472,500 3,500,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 500,000 0 0 0
CN 0 0 3,000,000 0 0
Totals 0 500,000 3,000,000 0 0
Report Date June 15, 2012 Page 1
AOL
Washbwaten , Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3
v
m A PIN /Project No B STIP ID D c s o
Z C Project Title D e3o
c D Road Name or Number o. 'a o c� r- �—'
m 0 3 E Begin &End Termini 'o Z 1 o, to .�
m F Project Description G Structure ID m' o o $ M o
00 WA -03942 28 0 No
Access ways in Dockside
to
Pave non - motonzed facilities
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 17,300 2,700 20,000
Totals 0 17,300 2,700 20,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 20,000
Totals 0 0 0 0 20,000
Report Date June 15, 2012 Page 2
Mokbigton t ,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 �
� a o
c 1z A PIN /Protect No B STIP ID 3 ° 3
z C Project Title
n c D Road Name or Number c CK o n
tv B E Begin 8 End Termini = n A Z ." o
a d F Project Description G Structure ID m a C y S o.
19 WA -03926 28 0 320 CE No
Armin Jahr Elementary Sidewalks Phase II
McClain
Sheridan Road to Stewart & E 31 st
Construct sidewalk infill on East side of McClain and the North side of E 31 st to
complete sidewalk construction south of the Elementary School as identified in the
City's Non - Motonzed Transportation Plan
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2013 STP(U) 100,000 0 0 100,000
P CN 2014 STP(U) 400,000 0 0 400,000
Totals 500,000 0 0 500,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th a 6th
PE 0 100,000 0 0 0
CN 0 0 400,000 0 0
Totals 0 100,000 400,000 0 0
Report Date June 15, 2012 Page 3
Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 <
v X c c
m o A PIN /Project No B STIP ID D c 0 3
C z C Project Title D 0 e3e a
0 9 9 c D Road Name or Number e=o c a a n °_'
m= 9 E Beg & End Termini Z ,� a m 5
H d IF Project Description G Structure ID m a o y a
14 WA -02834 03 C G O P S Yes
T
Arsenal Way /Patton Avenue Safety Improvements
to
Safety Improvements including curb, gutter, sidewalks, lighting, roadway widening,
and intersection improvements
Funding
Status Phase Phase Start Year (YYYlt) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2014 0 WSDOT 86,500 13,500 100,000
Totals 0 86,500 13,500 100,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 01 0 100,000
Totals 0 01 01 0 100,000
Report Date June 15, 2012 Page 4
AW Wro � o Six Year Transportation Improvement Program of TnnspWitathm
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 '<
� c 0
C A PIN /Project No B STIP ID 3 0 3
o Z C Protect Title y ee eo
2 c D Road Name or Number ezo a 'a o .'+ n r ° —' a
m 3 E Begin & End Termini M 'a 0 z . o
0 d � F Project Description G Structure ID ,o' o, � C � y � � a
14 WA -03938 21 C G O P S No
T
Bremerton Highway Safety Improvements - Phase II
to
Safety improvements at various locations as identified in the 2010 WSDOT report
that were not completed in the 2012 construction protect
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2014 0 WSDOT 103,800 16,200 120,000
P CN 2015 0 WSDOT 519,000 81,000 600,000
Totals 0 622,800 97,200 720,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th Sth & 6th
PE 0 120,000 0 0 0
CN 0 0 600,000 0 0
Totals 0 120,000 600,000 0 0
Report Date June 15, 2012 Page 5
AML
��,,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 �
m A PIN /Project No B STIP ID D o .°�.
i C Project Title D e a e °_' � xa
c D Road Name or Number a a o •'• c� r
E Begin & End Termini Z �� o, to .�
U) d F Project Description G Structure ID m a M G ,� y ,� a
19 WA -02827 28 O No
City Sidewalk Improvements
to
Repair, replacement and construction of deteriorated and missing or non - standard
sidewalk segments and handicap ramp installation throughout the City as identified in
the non - motorized transportation plan
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2013 0 WSDOT 572,250 87,750 660,000
P CN 2013 0 WSDOT 1,182,750 182,250 1,365,000
Totals 0 1,755,000 270,000 2,025,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 10,000 150,000 100,000 150,000 250,000
CN 15,000 350,000 150,000 350,000 500,000
Totals 25,000 500,000 250,000 500,000 750,000
Report Date June 15, 2012 Page 6
AWL
��, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 '<
V ego 'o
T — A PIN /Project No B STIP ID 3 0 3 c C
0 z C Project Title = y
_2 c D Road Name or Number A c a o c1
n E Begin 8� End Termini �' 3 0 3 V c
m 9 = z Q a
U) m F Project Description G Structure ID m a C w o
19 WA -02825 06 O No
City Street Pavement Preservation Program Local Streets - Non Federal Aid
to
Pavement preservation projects on non - federal aid eligible city streets Work
includes pavement and associated curb, gutter and sidewalks as identified in periodic
pavement/street condition reports
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2013 0 WSDOT 648,750 141,250 790,000
P CN 2013 0 WSDOT 10,163,750 1,835,500 11,999,250
Totals 0 10,812,5001 1,976,7501 12,789,250
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 40,000 150,000 150,000 150,000 300,000
CN 249,250 2,350,000 2,350,000 2,350,000 4,700,000
Totals 289,250 2,500,000 2,500,000 2,500,000 5,000,000
Report Date June 15, 2012 Page 7
�� Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 '<
V V
c A PIN /Project No B STIP ID 3 c 3 c 3
Z C Project Title y CD
C D Road Name or Number e ° c o K n ° — ' a
U 0 E Begin & End Termini .° Z .� 0 � S.
y d F Project Description G Structure ID m o o H CL
0 CL
14 WA -02826 06 O No
City Street Preservation Program Arterial Streets - Federal Aid Eligible
to
Pavement preservation projects on federal aid eligible city streets Work includes
pavement and associated curb, gutter and sidewalks as identifiedin periodic
pavement/street condition inventories
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2013 0 WSDOT 475,750 74,250 550,000
P CN 2013 0 WSDOT 6,401,000 999,000 7,400,000
Totals 0 6,876,750 1,073,250 7,950,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 50,000 100,000 100,000 100,000 200,000
CN 400,000 1,400,000 1,400,000 1,400,000 2,800,000
Totals 450,000 1,500,000 1,500,000 1,500,000 3,000,000
Report Date June 15, 2012 Page 8
Aft
VWa~on-' ;�,,� ,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 '<
° o
, n '— A PIN /Project No B STIP ID a c W 0 3
z C Project Title y ,c
CD Y M X
n c D Road Name or Number CD c c o .'+ n °—' a
d Cr E Begin & End Termini �
e� z m
U) m F Project Description G Structure ID m o. o e =r e �a
01 WA -02846 28 C O P S T Yes
W
Gorst- Sinclair Trail
to
Construction of a pedestnan and bicycle facility adjacent to SR3/166/304 from
Missouri Gate intersection at Naval Station Bremerton through Gorst to Port Orchard
City Limits
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2015 0 OTHER 86,500 13,5001 100,000
Totals 0 86,500 13,5001 100,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 100,000
Totals 0 0 01 0 100,000
Report Date June 15, 2012 Page 9
Depwbnmt o f �, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
T v
'o 0
m o A PIN /Project No B STIP ID D c c 3
z > Project Title n CD c a M
09 c D Road Name or Number c a o n m a
F 0 E Begin & End Termini Z ,� a m
m F Project Description G Structure ID m o o ,� ,� a
19 WA -02831 03 C G O P S CE Yes
TW
Harrison District Traffic Circulation Improvements
to
Various vehicular and pedestrian traffic circulation improvements in support of the
Harrison District Plan
Funding
Status Phase Phase Start Year (YYYlr7 Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P CN 2017 0 WSDOT 8,650 1,350 10,000
Totals 0 8,650 1,350 10,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
CN 0 10,000 0 0 0
Totals 0 10,000 01 0 0
Report Date June 15, 2012 Page 10
VU �,$ Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 �
V o
o A PIN /Pro ect No B STIP ID a y c 3
z C Project Title y e C W r'.
c D Road Name or Number m a 'a o n °—' a
F 0 B E Begin & End Termini V 3 Z ,V 0 m E-
H m F Project Description G Structure ID m o, o � a CL
? ;a CL
14 WA -03943 28 O P Yes
Kitsap Way at Harlow Intersection
to
Construct pedestrian facilities to provide safe crossing of Kitsap Way
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 34,600 5,400 40,000
Totals 0 34,600 5,400 40,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 40,000
Totals 0 0 01 0 40,000
Report Date June 15, 2012 Page 11
AIML � * Six Year Transportation Improvement Program of Thmsportation
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 '<
3 O O
O
m = A PIN /Project No B STIP ID 3 0 3 = o m
0 z C Project Title = a
2 c D Road Name or Number c a o •• 0 M
F 0 3 E Begin & End Termini 0 Z �e c
H
d i
m F Project Description G Structure ID m c, , o H r e `
17 WA -02830 28 C G O P T EIS Yes
W
Marine Drive Non - Motonzed Transportation Improvements
to
Provision of "safe haven" for pedestrians and bicyclists along Marine Drive from
Kitsap Way to the Terminus of Marine Drive
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 01 WSDOT 86,500 13,5001 100,000
Totals 01 86,500 13,5001 100,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 100,000
Totals 0 0 0 0 100,000
Report Date June 15, 2012 Page 12
AOL
o �,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 �
M c
m A PIN /Project No B STIP ID a c 0 3
z C Protect Title y e3o C
n c D Road Name or Number m c 'a o` •'+ n ero
F 0 B E Begin & End Termini = z •� CL •� q
H m F Project Description G Structure ID m a ,'. o e 9) c.
16 WA -03944 28 C G O P S 0 760 EA Yes
TW
Naval Avenue Road Diet
Naval Avenue
First Street to 15th Street
Reduce vehicle lanes and add bicycle lanes and pedestrian improvements
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 43,250 6,750 50,000
Totals 0 43,250 6,7501 50,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 50,000
Totals 0 0 01 0 50,000
Report Date June 15, 2012 Page 13
mo ,„,,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 '<
V 0 0
c A PIN /Project No B STIP ID D c o
z C Project Title y ,cY ..
C) 2 c D Road Name or Number c '� o n r i a
S" o 3 E Begin & End Termini = v 3 o c
y d F Project Description G Structure ID m a o y � CD o,
17 WA -02832 03 C G O P S No
T
Oyster Bay Avenue Improvements
to
Improvements (ind minor widening) to Oyster Bay Avenue from Kitsap Way to
Arsenal Way
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 259,500 40,500 300,000
Totals 0 259,500 40,500 300,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 300,000
Totals 0 0 01 0 300,000
Report Date June 15, 2012 Page 14
.,,,, Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Krtsap
MPO /RTPO PSRC Y Inside N Outside
m
CD
3 <
. A PIN /Project No B STIP ID a o 0 3
z C Project Title y e a � � � a �
c D Road Name or Number e °� c. o n r; °_'
d 9 E Begin & End Termini a 3 Z . o m
H d F Project Description G Structure ID m c G ,� a
14 /6585(001) BRE -9 04 C G O P S 0 260 CE No
T
Pacific Avenue Improvements
Pacific Avenue
6th St to 11th St
Rehabilitate and resurface Pacific Avenue (6th to 11th) Streetscape in Bremerton to
support redevelopmen5t of the Bremerton Urban Growth Center
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
S PE 2013 0 WSDOT 0 30,000 30,000
S CN 2013 0 WSDOT 2,595,000 405,000 3,000,000
Totals 0 2,595,000 435,000 3,030,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 30,000 0 0 0 0
CN 3,000,000 0 0 0 0
Totals 3,030,000 0 0 0 0
Report Date June 15, 2012 Page 15
WAF V � * Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 �
T °
c -Z A PIN /Project No B STIP ID 3 0 3 3
C Project Title a eo c
c D Road Name or Number c a 'a o n �
m 9 E Begin & End Termini oa m
H m F Protect Description G Structure ID m' a C H a
19 WA -03946 28 O 0 240 EA No
Shore Drive Shared Use Path
Upper Shore Drive
10th Street to Vandalia Ave
Convert upper portion of Shore Drive to a shared use pathway
Funding
Status Phase Phase Start Year (YYYI) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 34,600 5,400 40,000
Totals 0 34,600 5,4001 40,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 40,000
Totals 0 0 0 0 40,000
Report Date June 15, 2012 Page 16
Aft
W*shkwlion� Six Year Transportation Improvement Program
of Trmspwtath
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 '<
CD
o
m a A PIN /Project No B STIP ID n c c o 3
z C Project Title D e CD M
c D Road Name or Number °L o o .'+ n m
m 3 E Begin 8 End Termini i Z ., CL .�
aei m F Project Description G Structure ID m o, o $ H CD o,
14 WA -03927 04 O P CE No
Signal System Upgrades
to
Replacement of antiquated street signal system througout the City
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P CN 2014 STP(U) 1,000,000 0 0 1,000,000
Totals 1,000,000 0 0 1,000,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
CN 0 200,000 200,000 200,000 400,000
Totals 0 200,000 200,0001 200,000 400,000
Report Date June 15, 2012 Page 17
� Tran sportation
Six Year Transportation Improvement Program o f
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 �
M �o
m A PIN /Project No B STIP ID D c 0 9
Z C Project Title y e M
c D Road Name or Number e ° a o
H E Begin 8� End Termini Z C .� S.
w d F Project Description G Structure ID m a o w
14 WA -02838 04 C G O P S 2 920 EIS Yes
T
SR303 Corridor Improvements, Burwell to Riddell
SR303 (Warren Ave & Wheaton Way
Burwell St to Riddell Road
Reconstruction of the Warren Avenue/Wheaton Way (SR303) corridor to enhance
non - motonzed and transit facilities to connect residential neighborhoods with Olympic
College and Commercial Centers The project will address blight and improve the
business environment in Bremerton
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2015 0 WSDOT 2,984,250 465,750 3,450,000
P RW 2017 0 WSDOT 2,162,500 337,500 2,500,000
P CN 2017 0 WSDOT 1,730,000 270,000 2,000,000
Totals 0 6,876,7501 1,073,2501 7,950,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 250,000 2,000,000 700,000 500,000
RW 0 0 0 0 2,500,000
CN 0 0 0 0 2,000,000
Totals 1 01 250,0001 2,000,0001 700,000 5,000,000
Report Date June 15, 2012 Page 18
W*ShbVton State Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 '<
M a 'o
" '— A PIN /Project No B STIP ID D c o
z C Project Title y .3 � � � � o M
C D Road Name or Number CL 'a o n m o
d E Begin &End Termini s Z •� CL �'� S.
ai F Project Description G Structure ID m' CL o '1 y 5 a
16 WA -03929 21 O No
Street Lighting Improvement
to
Street light improvements for Ricky Road and Pine Road
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 21,625 3,375 25,000
P CN 2018 0 WSDOT 99,475 15,525 115,000
Totals 0 121,100 18,900 140,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 25,000
CN 0 0 0 0 115,000
Totals 0 0 0 0 140,000
Report Date June 15, 2012 Page 19
TV �t'Dtot* Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
M
3 <
m A PIN /Project No B STIP ID a o o
C Project Title y c > >o
c D Road Name or Number A a c. o '. n
U 0 B E Begin 8 End Termini -1 ,� Q, m
y m F Project Description G Structure ID m a 0 3 0 ? c
19 WA -03932 21 O No
Traffic Calming
to
Traffic Calming on local streets
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2013 0 WSDOT 24,125 3,375 27,500
P CN 2013 0 WSDOT 120,625 16,875 137,500
Totals 0 144,750 20,250 165,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 2,500 5,000 5,000 5,000 10,000
CN 12,500 25,000 25,000 25,000 50,000
Totals 15,000 30,000 30,000 30,000 60,000
Report Date June 15, 2012 Page 20
. ., � n Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
v V
co
A PIN/Project No B STIP ID D H 3
z C Project Title y X
c D Road Name or Number e=o a o. o m
m 0 a E Begin & End Termini =
y m F Project Description G Structure ID m a o $ w =r a
14 WA -03935 28 C G O P S 0 470 CE No
TW
Washington Avenue Complete Street
Washington Avenue
5th St to Pacific Ave
Reconstruct portion of Washington Avenue to widen sidewalk and add bicycle
Facilities
Funding
Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2014 0 WSDOT 500,000 0 500,000
P CN 2015 0 WSDOT 4,750,000 0 4,750,000
Totals 0 5,250,000 0 5,250,000
Expenditure Schedule
Phase list 2nd 3rd 4th 5th & 6th
PE 0 500,000 0 0 0
CN 0 0 4,750,000 0 0
Totals 0 500,000 4,750,000 0 0
Report Date June 15, 2012 Page 21
ANIL
VU �., Six Year Transportation Improvement Program
From 2013 to 2018
Agency Bremerton
County Kitsap
MPO /RTPO PSRC Y Inside N Outside
m
3 '<
3
A PIN /Project No B STIP ID 3 c 3 0 7
z C Project Title D eo ,c
n c D Road Name or Number c CL o n °—' a
H Q E Begin & End Termini z
w d F Project Description G Structure ID m o o eo a
17 WA -03934 03 O No
Wemer Road Widening & Signal
Wemer Road
to
Improvements to Wemer Road
Funding
Status Phase Phase Start Year (YYYI() Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds
P PE 2018 0 WSDOT 259,500 40,500 300,000
P CN 2015 0 WSDOT 2,335,500 364,500 2,700,000
Totals 0 2,595,000 405,000 3,000,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
PE 0 0 0 0 300,000
CN 0 0 0 0 2,700,000
Totals 0 0 0 0 3,000,000
Federal Funds State Funds Local Funds Total Funds
Grand Totals for Bremerton 4,527,5001 38,307,050 5,944,700 48,779,250