RESOLUTION WAIVING LIgUIDATFD_DAMAGES
WHEREAS, The City of Bremerton, as party of the first part,
has heretofore entered into an agreement to complete work on the
North Bremerton Sewer System, under Contract 3 of P.W.A. Docket
No. Wash. 1362 -.D, which said work was to be done by N. Coluccio and
Company, Contractors; this work should, according to the Contract,
have been completed by September 11th, 1938, but owing to the delay
in approving the contract documents, delaying the start of said work,
and the delay in securing motors for the pumping units and there,was
in their contract a provision that they should pay the sum of $25.00
per day as liquidated damages to the party of the first part for each
and every day after September 11th, 1938, until the completion of their
contract;
NOW, TBESMRE, The party of the first part, the City of Bremerton,
hereby waives the liquidated damages mentioned in said contract and
agrees to relieve the said Contractor from the payment thereof on account
of the facts above stated.
PASSED BY THE CITY COMMISSION of the City of Bremerton, signed by
the Mayor and attested by the City Clerk in authentication of such
passage this day of Qawbar, 1938, A.D.
MAYOR
ATTEST:
CITY C