HomeMy WebLinkAbout5056 Contract Number: 5056 Vendor: STAN PALMER CONSTRUCTION, INC. Subject: Sewage Pump Station CE -1 Upgrade Department: Engineering File Class: LEG 12 -1 Begin Date: 8/2/2011 End Date: 4/23/2012 Review Date 1/1/2012 Vault Date: Comments. Change Order #1 $15,052.87, Change Order #2 $50,000.00; Change Order #3 2/23/12 Add 44 days; Change Order #4 3/31/12 Add 40 Days CITY OF BREMERTON CHANGE ORDER CONTRACT CHANGE ORDER NO 4 PROJECT NAME Sewage Pump Station CE -1 Upgrade PROJECT NO 5337 CONTRACTOR Stan Palmer Construction ORIGINAL CONTRACT AMOUNT 542,457 00 DAYS 180 PREVIOUSLY APPROVED CHANGES 65,052 87 DAYS 44 THIS CHANGE 000 DAYS 40 REVISED CONTRACT AMOUNT 607,509 87 DAYS 264 This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items The increase or decrease in contract price shown below includes any applicable taxes DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT 0 CONTRACT CONTRACT TIME •- AMOUNT AMOUNT EXTENSION :3 ($) ($) (DAYS) X The current Substantial Completion date is March 14, 2012 -- -- 40 The 40 -day extension is granted, revising the Substantial Completion date to April 23, 2012 NET CHANGE IN CONTRACT AMOUNT -- -- 40 INCREASE OR (DECREASE) ESTIMATED SALES TAX AT 8 6% -- -- -- TOTAL INCLUDING SALES TAX 000 -- -- Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on -site or home office overhead, or lost profits Nothing in this Change Order shall limit the City's right to bring a claim for past performance •� L4 r " - CONTRACT CHANGE ORDER NO 4 PROJECT NAME Sewage Pump Station CE -1 Upgrade The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order This document will become a supplement of the contract and all provisions will apply hereto It is understood that this Change Order shall be effective when approved by the City of Bremerton The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract In addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change CONTRACTOR Approved DATE 3 /Z PROJECT MANAGER Recommended DATE CITY ENGINEcAM Council act on is required as project cost will exceed approved budget ❑ Yes 15 No Council action is required as change exceeds Mayors authority per BMC 2 76 110 ❑ Yes a No Recommended _ DATE DIRECTOROF PUEILIC WORKS AND UTILITIES' Recommended DATE 3 - lZ MAYOR Approved DATE APPROVED AS TO FORM: ATT ^trdmerton City Attorney City Nerk Page 2 of 2 Contract Number: 5056 Vendor. STAN PALMER CONSTRUCTION, INC. Subject Sewage Pump Station CE -1 Upgrade Department: Engineering File Class- LEG 12 -1 Begin Date: 8/2/2011 End Date: 3/14/2012 Review Date: 1/1/2012 Vault Date: Comments: Change Order #1 $15,052 87 Change Order #2 $50,000.00 Change Order #3 2/23/12 Add 44 days CITY OF BREMERTON CHANGE ORDER CONTRACT CHANGE ORDER NO 3 PROJECT NAME Sewage Pump Station CE -1 Upgrade PROJECT NO 5337 CONTRACTOR Stan Palmer Construction ORIGINAL CONTRACT AMOUNT 542,457 00 DAYS 180 PREVIOUSLY APPROVED CHANGES 65,052 87 DAYS 0 THIS CHANGE 0 00 DAYS 44 REVISED CONTRACT AMOUNT 607,509 87 DAYS 224 This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items The increase or decrease in contract price shown below includes any applicable taxes DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT C) CONTRACT CONTRACT TIME AMOUNT AMOUNT EXTENSION ($) ($) (DAYS) x In correspondence dated January 25, 2012, the Contractor -- — 44 requested a time extension of 44 days due to poor weather, late delivery of City- purchased pumping equipment, and modifications to the pump layout The City has reviewed the documentation and agrees that the delays were beyond the control of the Contractor and an equitable time extension is justified in accordance with Paragraph 12 03 of the General Conditions (00700) The current Substantial Completion date is January 30, 2012 The 44 -day extension is granted, revising the Substantial Completion date to March 14, 2012 NET CHANGE IN CONTRACT AMOUNT -- -- 44 INCREASE OR (DECREASE) ESTIMATED SALES TAX AT 8 6% -- -- — TOTAL INCLUDING SALES TAX 000 -- 44 Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on -site or home office overhead, or lost profits Nothing in this Change Order shall limit the City's right to bring a claim for past performance CONTRACT CHANGE ORDER NO 3 PROJECT NAME Sewage Pump Station CE -1 Upgrade The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order This document will become a supplement of the contract and all provisions will apply hereto It is understood that this Change Order shall be effective when approved by the City of Bremerton The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract In addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change CONTRACTOR Approved DATE Z PROJECT MANAGER V/ Recommended DATE 2 �2 CITY ENGINEER Council action is re fired as project cost will exceed approved budget ❑ Yes (9 No Council action is re uired as change exceeds Mayors authority per BMC 2 76 110 ❑ Yes ® No Recommended °� DATE Zli o A �-- DIRECTOR OF PU LIC WORKS AND UTILITIES Recommended DATE 2 -1 4r Z MAYOR Approved DATE APPRO AS TO FORM: EST: 4 T erton i Attorney City Clerk Page 2 of 2 January 25, 2012 Department of Public Works Engineering Division 3027 Olympus Drive Bremerton, WA 98310 Attn Bill Davis, PE RE Sewage Pump Station CE -1 Upgrade, Project No 5337, Time Extension Request Dear Bill, Over the past eight weeks there have been a series of events that has made it impossible for us to complete the CE -1 Pump Station project by the required date of January 31, 2012 Specific events that have delayed the work are, 1 Weather delays that impacted the installation and tie in of the exterior force main 2 Late delivery of the City provided pumps 3 Changes to the pump discharge piping required because of differing pump alignment 4 Weather delays from January 11 �' to present We are still being delayed by the weather and don't anticipate being able to resume full speed in our efforts until the second week of February Our original construction schedule showed project completion on January 23, 2012 Our updated schedule submitted to account for the late pump delivery indicated a February 28, 2012 completion Based on the above reasons we request that a contract time extension of 44 calendar days be given Sincerely, J Na#a Todd Haga Project Manager 5107 State Hwy 3 SW, Bremerton, WA 98312 (360- 674 -2100) Fax (360)- 674 -7190 Contract Number: 5056 Vendor: STAN PALMER CONSTRUCTION, INC. Subject: Sewage Pump Station CE -1 Upgrade Department: Engineering File Class LEG 12 -1 Begin Date. 8/2/2011 End Date: 12/31/2011 Review Date: 1/1/2012 Vault Date. Comments: Change Order #1 $15,052.87 Change Order #2 $50,000.00 CITY OF BREMERTON CHANGE ORDER CONTRACT CHANGE ORDER NO PROJECT NAME Sewage Pump Station CE -1 Upgrade PROJECT NO 5337 CONTRACTOR Stan Palmer Construction ORIGINAL CONTRACT AMOUNT 542,457 00 DAYS 180 PREVIOUSLY APPROVED CHANGES 000 DAYS 0 THIS CHANGE 15,052 87 DAYS 0 REVISED CONTRACT AMOUNT 557,509 87 DAYS 0 1 This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items The increase or decrease in contract price shown below includes any applicable taxes DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT o CONTRACT CONTRACT TIME AMOUNT AMOUNT EXTENSION (DAYS) X Complete additional electrical work, including pulling wire, 13,860 84 , 0 installing circuits and making connections, to make flowmeter, vault items, trolley, actuators, and other electrical items active as described in the attached documentation The scope of this work was originally going to be performed by City Wastewater (WW) staff However, due to time and staffing constraints, the electrical subcontractor will now complete this work NET CHANGE IN CONTRACT AMOUNT 13,860 84 INCREASE OR (DECREASE) ESTIMATED SALES TAX AT 8 6% 1,192 03 TOTAL INCLUDING SALES TAX 15,052 87 Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, Including, without limitation, claims related to contract time, on -site or home office overhead, or lost profits Nothing in this Change Order shall limit the City's right to bring a claim for past performance CONTRACT CHANGE ORDER NO 'I PROJECT NAME Sewage Pump Station CE -1 Upgrade The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order This document will become a supplement of the contract and all provisions will apply hereto It is understood that this Change Order shall be effective when approved by the City of Bremerton The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract in addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change CONTRACTOR Approved DATE /d- 7 PROJECT MANAGER Recommended DATE CITY ENGINEER Council action is required as project cost will exceed approved budget ❑ Yes E '1 o Council action is required as change ex authority per BMC 2 76 110 ❑ Yes 13'1 o Recommended DATE DIRECTOR OF WORKS AND UTILITIES Y Recommended DATE 1107k 2f MAYOR Approved DATE Z2 -Dfl --?elf i APP TO FORM: ATTEST: Br r/erton CiVy Attorney C C erk I I i Page 2 of 2 STAN PALMER CONSTRUCTION CHANGE ORDER PROPOSAL PROJECT Sewage Pump Station CE -1 Upgrade DATE 10/7/2011 Revised 11 /l /11 TO Department of Public Works SPC CO NO X -101 Engineering Division 3027 Olympus Drive Bremerton, WA 98310 DESCRIPTION Provide electrical changes as requested DIRECT COSTS FROM WORK SHEET 1 LABOR 0 00 direct labor w /fringes safety & insurance 2 EQUIPMENT OWNED 000 Direct equipment costs 3 RENTAL EQUIPMENT 000 Direct rental costs 4 MATERIALS 000 Direct material costs 5 SMALL TOOLS 0% 000 On Direct Labor Costs 6 DIRECT SUPERVISION 0% 000 On Direct Labor Costs 7 SUB TOTAL 000 Prime contractor Direct Costs, small tools & supervision 8 SUBCONTRACTORS 12,133 09 Subcontractor Costs See Attached Deno Electric 9 MARK UP ON LABOR 29% 000 MARKUP ON MATERIALS & SERVICES 29% 000 MARKUP ON EQUIPMENT 29% 000 10 MARK UP ON SUBCONTRACTORS 12% 1,45597 11 SUBTOTAL 13,589 06 Total Prime and Subcontractors 12 Bonds and Insurance (2% of lines 1land 12) 2% 27178 Bond and Insurancce on increased contract amount 13 Total Change Proposal Cost 13,860 84 Total Change Proposal (Not including Washington State SalesTax) d � 9� -0 PROPOSAL (3 D ENO ELECTRIC CORPO 6 RAT1 2 0 5 7 N 8193 7 OUTBACK AVENUE NW, SILVERDALE, NVA 98383 -6300 PROPOSAL DATE ' CONTR ;1DEN0EC`001B6 FED ID #91- 2010755 FAX #(360) 698 -2178 10/07/11 1 BILL TO SHIP TO STAN PALMER CONSTRUCTION INC STAN PALMER CONSTRUCTION INC 5107 STATE HWY 3 SW PUMP STATION CE1, PARK AVENUE BREMERTON, WA 98312 BREMERTON, WA 98312 PROJECT PO NO TERMS EXPIRATION DATE CE 1 PUMP STATION Net 30 11 /06/11 DESCRIPTION QUANTITY COST AMOUNT COST OF MATERIAL TO COMPLETE WIRING AS REQUIRED, 1 3,14766 3 147 66 NOT INCLUDING FLOWMETER MANUFACTURER CABLE (FOR REMOTE INTERCONNECT), NOT INCLUDING CIRCUIT BREAKERS OR PANEL REVISIONS IF REQUIRED TO CONNECT VALVE OPERATOR AND VAULT CIRCUITS, INCLUDES PUMP WIRING ONLY TO NEW VFD'S (FURNISHED AND INSTALLED BY OTHERS) COST OF LABOR 115 6055 6,963 25 SUBTOTAL 10,110 91 OVERHEAD AND PROFIT 20% 02 10,110 91 2,022 18 RESELLER #A15 5931 11 EXP 12/11 000% 000 Total $12,133 09 All material is guaranteed to be as specified All woi k to be completed in a workmanlike manner according to standai d pi actices Any changes or additions to above specifications involving extra costs will be belled on a time and material basis or as agreed to in writing Time of completion is contingent upon delays due to causes beyond our control This proposal is void if not accepted by erpirotion date above Owner will carry fire, liability, and other necessary insurance State and local taxes are not included ACCEPTANCE OF PROPOSAL The above prices, specifications, terms, and conditions ai e satisfactory and hereby accepted You are authorized to do the work as specified Payment will be made as specified above This proposal also serves as an intent to lien and receipt is hereby acknowledged Bs; Date _ Please sign crud retui n one copy jor acceptance Thank you for the opportunity to quote your pi oject i � I ✓'rORK [ ,J yy I' q w �,.,.._a •g�'�1,ATEG B; ". _ n R Pn10ED - EX7E JDEC Sv Et - ECrED BY I � I MA - ER,AL OUANTITv I MATER - AL PQ,CE I °ER MATERIAL EXTENSION LABOR JNIT PEF { ASOR ( EXTENSION t oft? g'c� T � 5("f- t y Jao I if+s F 1 1 - ` 3 Y `c�ov r r do 2 COLA e0111 , 4,( 1 vivo °_ Ile.v I L � � � I f � �� = �n.YoiL 4r1 / a _ 3 -3 X / �o`t Pe,6 eft tf? �7� {�3 � t I I WW r El to 1 ( I 4,1 5 �—P e AJC j ff' QVS� %f"I { >' I F.' tw -` -?� F � •` Jot Y ;+ F v -Z`l- .yy /� 4 �°T` 00 9 - e b- nz - o-o'x 114 �E G° F - 2 J PJp P r x = t a (tom 9 YYYYYY r l � r '.~_ 2vn to _Jef.c/ t, T.0 It 6 . 12 f V m �t 1.4 _ = , i Ine / rvt f A/I U ; � �1t � G � t' �� � n� i� 00 C, t 0� i -` r_. r,, s R B W ' f' ctrr�dur 3100 I �3!0© M ( i { 1 i �3 { i $C3 f3Q�_-,5a a /� 00 z, c o o r /S " SS 6 0 I X 3 4 E F � �� OF� Do, � TM ` ��2 22 ear' ' ° j z t ' I I �.I• " '� 1` �a� - = 50 "c3 f'�fr 4� - 1 Z ' v P ,%''F O'!} 24 �� i E } f ! `i� C� �`r s� J� j 'I 1 TAP C6F TC FULLFY i �� i 1 00 G i� `T-'Iqp� "; 26� I ?'t D{ re, L EI' I 30 ! � � ' I 1 ' " [-7[a 27 L ( I , ST 0'� ff I f f t - a E I f I a : q { ; !ooI r�i_ } 28 - C �} JrV3 I t CvJ}SJ. E LAF f t !j i lb l r t 1 � 1 { r ( 0 Q 1 (' �5 G Iff�� 0 I /100 �• c I f .2 cic s al -c 7---„ -,r.:z i a Re_,7 ?1 '.' IT-, C� 4 ESII� ATE No WORK t� �f�' V c fE - I — , re- � I sree Of l S VO St- I EST'RffiT s8 ?= ^�O BY- E),TEN:)ED S" - 1i"CIED S, Y I /, { 1 LABOR i 1.5 i J MATERIAL QUANTITY dFATERiA! PRIDE + RED MATERIAL EXTENSION LABOR UNiT RER EXTENSION f � vv - Lv +So +sue aa`/o ti-a Jac till 1 � ll � � 00�s ° � 00 Irk ° 2 3 l` x h` Yciv`a ,�{C3 t:3 ' - 4 0 YkA 00 l � 6 � f ( 001 c 1 = 1 8 0 s "3 -iW ��e t {00 ELI /`l /j pCffor SS (/J �.r { 3^�S E r r :r r, q('1 0 3 /r� �' i ` X C° I i� L) E - M 1 6 - 4s' 01 so C- 11 2 ! se k t'altf� � 12 s reokfp 1t/ t, PaNel ,3 fix, ctKe_ :� iN Ufa 2 `�" lf'dn'�t - { ' I Y;f � ?=fi�. { dlS �60 I 14 1 VA t� �,j V 5 � " � 1T 7 15 `!` 91,3 m ` f (��T9'SK tai Y .6 � "-# 6 00 I i 1 0� G f - r✓¢ F { � � i t70 f} �` WO CE�eUf ✓1Fic G BNCF Si Armel s 7 ; F -, I Jt? - T - S i `1 = >� + I f - > { �' ^ �C (�o C, I , : -, So 22 7 I I - - 23 24 251 I r ,o PLc py -Per' / 3 xPs $' �$� 00 j rri I I { t Sr i = 00 26 i I -' 27 �rEd;�f o FR J rir-, PL c ; ' C_ �,-- I I I ` —{ _h ' CZ 0i E�' ' 2e) J / �f K �f�� i I i r i 1 i' qI P >s �1 33o Cis aal i f,� rII�IaI� f T - 1 - 1 981 2 30 171E A !'-C �.! L s H F h L '" E r (T'! C¢! th/ 'P.aP�cG cif 5 R! YAP a t J I i I r5i i G- ) I i" � 'J' (30 7 CSI 132 S--, Tar =r .d T Zs. r ? r- 17' L CITY OF BREMERTON y CHANGE ORDER CONTRACT CHANGE ORDER NO 2 PROJECT NAME Sewage Pump Station CE -1 Upgrade PROJECT NO 5337 CONTRACTOR Stan Palmer Construction ORIGINAL CONTRACT AMOUNT 542,457 00 DAYS 180 PREVIOUSLY APPROVED CHANGES 15,052 87 DAYS 0 f THIS CHANGE 50,000 00 DAYS 0 REVISED CONTRACT AMOUNT 607,509 87 DAYS 0 This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items The Increase or decrease In contract price shown below Includes any applicable taxes DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT CONTRACT CONTRACT TIME AMOUNT AMOUNT EXTENSION (DAYS) W W X Establish a contingency (force account) allowance for the sole 46,040 52 0 use of the Owner to cover unanticipated costs, in accordance with paragraph 11 02 C 1 of the Standard General Conditions (Section 00700) NET CHANGE IN CONTRACT AMOUNT 46,040 52 INCREASE OR (DECREASE) ESTIMATED SALES TAX AT 8 6% 3,95948 TOTAL INCLUDING SALES TAX 50,000 00 Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, Including, without limitation, claims related to contract time, on -site or home office overhead, or lost profits Nothing In this Change Order shall limit the City's right to bring a claim for past performance II CONTRACT CHANGE ORDER NO 2 PROJECT NAME Sewage Pump Station CE -1 Upgrade The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order This document will become a supplement of the contract and all provisions will apply hereto It is understood that this Change Order shall be effective when approved by the City of Bremerton The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract In addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change CONTRACTOR A rove DATE 4 7 11 PROJECT MAN O Recommended DATE 1Z CITY ENGINEER Council action is required as pro ct cost will exceed approved budget ❑ Yes Ef No Council action is required as c nge exceeds Mayors authority per BMC 2 76 110 ❑ Yes 6d Z Recommended DATE �zl� 3��1 DIRECTOR OF PUBLIC WORKS AND UTILITIES Recommended DATE 1 Pex- MAYOR A roved ATE Z 2-D� '0/ D T D AS TO ORM: ATTEST: P B/ rmertoA City Attorney City Clerk Page 2 of 2 Contract Number: Vendor: Sub�ect: Department: File Class: Begin Date: End Date: Review Date: Vault Date: Comments : 5056 STAN PALMER CONSTRUCTION, INC. Sewage Pump 5tation CE-1 Upgrade Engineering LEG 12-1 8/2/2011 12/31/2011 1/1/2012 . ' ' ' 1 � I� ' AGREEMENT SECTION 00500 THIS AGREEMENT is dated the 22nd day of �uly m the year 2011 by and between C�ty of Bremerton (hereinafter called OWNER) and Stan Palmer Construction, Inc (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows ARTICLE 1 WORK CONTRACTOR shall complete the WORK as specified or indicated in the OWNER's Contract Documents entitled Sewage Pump Station CE-1 Upgrade ARTICLE 2 CONTRACT TIMES ' Substantial Completion for the WORK must be achieved not later than 180 calendar davs from the date of Notice to Proceed Final Completion and Acceptance of the Work must be achieved not later than 30 calendar days after Substantial Compietion ' ' ' 1 ' ' 1 1 1 ARTICLE 3 LIQUIDATED DAMAGES OWNER and the CONTRACTOR recognize that time is of the essence of this Agreement and that the OWNER wdl suffer financial loss if the WORK is not completed within the time specified in Article 2 herem, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions and Supplementary Conditions They also recognize the delays, expense, and difficulties involved in proving m a legal proceedmg the actual loss suffered by the OWNER if the WORK is not completed on time Accordingiy, instead of requiring any such proof, the OWNER and the CONTRACTOR agree that as liquidated damages for delay (but not as a penalry) the CONTRACTOR shail pay the OWNER $1000 for each day that expires after the time specified in Article 2 ARTICLE 4 CONTRACT PRICE OWNER shall pay CONTRACTOR for compietion of the WORK in accordance with the Contract Documents in current funds the amount set forth m the Bid Schedule(s) (Contractor Initials) ' SEWAGE PUMP STATION CE-1 UPGRADE JUNE 2011 AGREEMENT 00500-1 I� r t , ' ' ' ' 1 ' � ' ' � ' ARTICLE 5 PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions Applications for Payment wdl be processed by ENGINEER as provided in the General Conditions ARTICLE 6 CONTRACT DOCUMENTS The Contract Documents which comprise the entire agreement between OWNER and CONTRACTOR concemmg the WORK consist of this Agreement (Section 00500) and the followmg attachments to this Agreement • Notice Inviting Bids (Section 00030) • Instructions to Bidders (Section 00100) � Bid Forms including the Bid, Bid Schedule(s), Information Required of Bidder, Bid Bond, and all required certificates and affidavits (Section 00300) • Performance Bond (Section 00610) • Payment Bond (Section 00620) • General Conditions (Section 00700) • Supplementary General Conditions (Section 00800) • Technical Specifications as listed in the Table of Contents, including appendices • Drawings as listed in the List of Drawings • Addenda numbers 1 to 1, inclusive • Change Orders which may be delivered or issued after Effective Date of the Agreement and are not attached hereto There are no Contract Documents other than those listed in this Article 6 The Contract Documents may ' only be amended by Change Order as provided in Paragraph 3 04 of the General Conditions ARTICLE 7 INDEMNIFICATION ' The CONTRACTOR and OWNER acknowledge and agree that they have negotiated the following in accordance with the reqwrements of RCW 4 24 115 and the CONTRACTOR speaficaliy waives his immurnty under mdustrial insurance under Title 51 RCW The CONTRACTOR and OWNER acknowledge ' and agree to the reqwrements for indemnification in Section 00800 SC-6 20 The provisions of this article shall survive the termination or expiration of this agreement ' I ' (Contractor Irntials) SEWAGE PUMP STATION CE-1 UPGRADE JUNE 2011 AGREEMENT 00500-2 ' Y ` ' , ' , ' , ' ' � ' � ' ' I� I u i' ARTICLE 8 SUSPENSION OF WORK AND TERMINATION The Contractor agrees to the indicated in Article 15 of (Suppiementary Conditions) ARTICLE 9 ASSIGNMENT right of the OWNER to suspend work or termmate this agreement as Section 00700 (Standard General Conditions) and Section 00800 No assignment by a party hereto of any rights under or interests in the Contract Documents wiil be binding on another party hereto without the wntten consent of the party sought to be bound, and speafically but without limitation mornes that may become due and mornes that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless speaficaily stated to the contrary in any written consent to an assignment, no assignment wdl release or discharge the assignor from any duty or responsibdity under the Contract Documents The OWNER, in its sole discretion, may refuse to allow the CONTRACTOR to assign any or all of its duties, rights and/or responsibilities under the Agreement, except with regards to an assignment of funds for security purposes In the case of an assignment for security purposes the OWNER may condition its approval to the extent it deems necessary to assure that there wdi be adequate funds to complete the WORK and to pay a subcontractors and suppliers OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect of ali covenants, agreements and obligations contained in the Contract Documents IN WITNESS WHEREOF, OWNER and CONTRACTOR have caused this Agreement to be executed the day and year first above written Ap ve s t Sig a ure) . �� '' (Title) SEWAGE PUMP STATION CE-1 UPGRADE JUNE 2011 CONTRACTOR Stan Palmer Construction, Inc By - CORPO E SEAL] Todd Haga, Vice-President Attest i,IM �� p ��.�„ Jo depard V1A ess Address for givmg notices 5107 State Hwy 3 SW, Bremerton, WA 98312 License No ST-AN-PC= 202NF Agent for seroice of process Propel Insurance (Max Hanley) AGREEMENT 00500-3 ' Address for giving notices G cc� 3�s �-��� � � ��� � � 9�33�