HomeMy WebLinkAbout03/17/2010 5H DATE SUBMITTED: March 3, 2010
AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Acceptance of Easement for Committee Meeting Date: March 10, 2010
W580 Zone Reservoir from the City of Port COUNCIL MEETING Date: March 17, 2010
Orchard. Department: PW &U Engineering
Presenter: Michael Mecham
Phone: 473 -5288
SUMMARY: Several years ago, the City of Bremerton and the City of Port Orchard entered into an
agreement for joint water use in the Anderson Hill and McCormick Woods area. The intent of the
agreement was as development occurs in that area both water systems would become independent, but
until that time it was felt that it was prudent to have a joint use agreement. As part of that agreement,
the City of Port Orchard was to give the City of Bremerton an easement to construct a 580 pressure
zone reservoir. This agenda bill is to accept the conveyance of an easement to build a W580
reservoir. Although the construction of the new W580 reservoir will not happen for a few years, it
sets the stage for the reservoir to be built.
ATTACHMENTS: 1. Council Summary; and 2. Water Reservoir Easement
FISCAL IMPACTS (Include Budgeted Amount): None.
APPROVALS:
DEPARTMENT DIRECTOR: �— r
CITY ATTORNEY:
FINANCE DIRECTOR:
MAYOR:
COMMITTEE CHAIR
COUNCIL PRESIDENT: CONSENT AGENDA
GENERAL BUSINESS ❑
PUBLIC HEARING ❑
RECOMMENDED MOTION: Move to approve the Easement for W580 Zone Reservoir and
authorize the Mayor to finalize and execute the agreement with substantially the same terms and
conditions as presented.