Comments: Change Order #1 -9/09
ACCEPTANCE OF COMPENSATION & RELEASE OF ALL CLAIMS
Warehouse and Maintenance Building Additions
Project No. 4403 and 4426 — City Contract No. 4782
Unimark, Inc. hereby indicates agreement with, and acceptance of, the final Progress
Payment and total Contract Price of $465,189.20, including Washington State sales
and/or use taxes, and the final Contract Time of 140 calendar days, as full and final
compensation for all Work performed in connection with Contract Number No. 4782, and
does hereby release the City of Bremerton from all claims, liability, demands, damages
and actions of any kind whatsoever, arising from performance of that Contract.
Unimark, Inc.
By: Date: 1 to I O
Title: P ttoaCC T' MANAGEk
r '
CertiT6tV `ffist
�,. . — .
Sif skft an4c,� fy before me this f Q day of
/ CA
f ��n►ua�"``�
�� /b�
NS3a``'.��,
sA
AFFIDAVIT OF PUBLICATION
�1
s
Account # 42742 AD# 255326
STATE OF WASHINGTON
COUNTY OF KITSAP
I, Laura Wessels, being first duly sworn on oath, deposes and says: That she is now, and at all times
embraced in the publication herein mentioned was the principal clerk of the printers and publishers of
KITSAP SUN; that said newspaper has been approved as a legal newspaper by order of the Superior Court
of the County of Kitsap, in which County it is published and is now and has been for more than six months
prior to the date of the publication hereinafter referred to, published in the English language continually as
a daily newspaper in Bremerton, Kitsap County, Washington, a weekly newspaper in Kitsap County,
Washington and is now and during all of said time, was printed in an office maintained in the aforesaid
place of publication of said newspaper; that the following is a true text of an advertisement as it was
published in regular issues (and not in supplement form) of said newspaper on the following date, to wit: A
November 25, 2009 and that such newspaper was regularly distributed to its subscribers during all of said
period. That the full amount of the fee charged for the foregoing publication is the su of $41.56. This
amount has not been paid in full.
(Signature of Principal Clerk) �pp� g2 4 T *'�,,'
Subscribed and sworn to before me this day of December 4, 2009.
co ; it 's s
Notary Public in and for the State of Washington, Kitsap County. i
• X01
NOTICE OF COMPLETION
Notice of Completion has been issued to Unimark, Inc. for City Project No. 4403 and 4426, City Contract
No. 4782 for the Warehouse and Maintenance Building Additions. Any parries having a claim for material,
labor or damages related to this Contract have forty-five (45) days from the date of first publication of this
notice to file a claim.
Carol Etgen
City Clerk
345 6th Street
Bremerton, Washington 98337
November 25, 2009 ...................AD #20094760
Washington State
OPP ir!WOW of Department of Revenue
v PO Box 47474
Olympia, WA 98504 -7474
602174203
Certificate of Payment of State Excise
Taxes by Public Works Contractor
UNIMARK INC CITY OF BREMERTON PUBLIC WORKS
1221 FOURTH AVE COLEN COREY
SEATTLE WA 98101 3005 3027 OLYMPUS DR
BREMERTON WA 98310 4799
We hereby certify that taxes, increases and penalties due or to become due from the above -named
contractor under Chapter 180, Laws of 1935, as amended, with respect to the following public works
contract:
CITY OF BREMERTON PUBLIC WORKS
4845, WAREHSE & MAINT BLDG ADDNS
together with all other taxes, increases and penalties due from such contractor, have been paid in full or that
they are, in the Department's opinion, readily collectible without recourse to the state's lien on the retained
percentage.
This certificate is issued pursuant to the provision of Chapter 60.28 Revised Code of Washington for the
sole purpose of informing the state, county, or municipal officer charged with the duty of disbursing or
authorizing the payment of public funds to said contractor that the Department of Revenue hereby releases
the state's lien on the retained percentage provided by this Chapter for excise taxes due from said contractor.
This certificate does not release said contractor from liability for additional tax that may be later
determined to be due with respect to the above - mentioned contract or other activities.
Dated C2 � 0 at Olympia, Washington,
State of Washington
Department of Revenue
Gr�
Certifying Officer
For tax assistance, visit dor.wa.gov or call 1- 800 -7706. To inquire about the availability of this document in an alternate format for the visually impaired ,
please call (360) 705 -6715. Teletype (TTY) users may call 1 -800- 451 -7985.
REV 310028 (10- 01 -02)
Verify Workers' Comp Premium Status - Employer Liability Certificate Page 1 of 1
Washington State Department of STA Employer Liability
Labor and Industries: " 3 °: Certificate
1 $9
Department of Labor and Industries
Employer Liability Certificate
Date: 01/06/2010
UBI #: 602 174 203
Legal Business Name: UNIMARK CONSTRUCTION GROUP LLC
Account #: 025,106 -00
'Doing Business As' Name: UNIMARK CONSTRUCTION GROUP LLC
Estimated Workers Reported: Quarter 3 of Year 2009 "31 to 50 Workers"
(See Description Below)
Workers' Comp Premium Status: Account is current. Firm has voluntarily reported and
paid their premiums.
Licensed Contractor? Yes
License: UNIMACG984CA
Expire Date: 2/1/2010
Account Representative: T2 / KATHY WITHERS (360)902 -4829 - Email:
WITE235 @lni.wa.gov
What does "Estimated Workers Reported" mean?
Estimated workers reported represents the number of full time position requiring at least 480
hours of work per calendar quarter. A single 480 hour position may be filled by one person, or
several part time workers.
Industrial Insurance Information
Employers report and pay premiums each quarter based on hours of employee work already
performed, and are liable for premiums found later to be due. Industrial insurance accounts have
no policy periods, cancellation dates, limitations of coverage or waiver of subrogation (See RCW
51.12.050 and 51.16.190
�
https: // fortress. wa. gov/ lni/ crpsi /AcctlnfoPrint.aspx ?Accountld= 02510600 &AccountManage... 1/6/2010
1
Employment Security r
----- 7 WASHINGTON STATE _.
CONTRACTOR: UNIMARK INC ) CERTIFICATE OF
1221 4TH'AVE ) PAYMENT OF CONTRIBUTIONS
SEATTLE, WA '98101 ) PENALTIES AND INTEREST ON
PUBLIC WORKS CONTRACT
ES Reference No. 183052-007
TO: CITY OF BREMERTON
3027 OLYMPUS DR
BREMERTON, WA' 98310
The Employment Security Department hereby certifies those contributions, ns, penalties and interest
due from the above named contractor under the Employment Security Act have been paid in full _or =
provided for with respect to the following public works contract:
• 4845
The Employment Security Department hereby certifies that it has no claim pursuant to RCW
50.24.130 against the public body named above for tax attributable to service performed for said public
body by the above named contractor on the above described contract. The Employment Security
Department releases its lien on the retained percentage, which is provided by RCW 60.28.040 for
contributions, penalties and interest due from said contractor.
This certificate does not release said contractor from liability for additional contributions,
penalties and interest which may be later determined to be due with respect to the above mentioned
contract.
Dated at Olympia, Washington on December 11, 2009.
COMMISSIONER
EM ENT SECURITY DEPARTME T
B
(Authorized Represe tive)
Original— Disbursing Officer
Duplicate— Employer
Triplicate— Central Office Files
• EMS 8449 760 R3 -98
Contract Number:
Vendor:
Subject:
Department:
File Class:
Begin Date:
End Date:
Review Date:
Vault Date:
Comments:
4782
UNIMARK CONSTRUCTION GROUP LLC
Warehouse & Maintenance Building Additions - PW&U
Engineering
LEG 12-1
01/22/2009
10/31/2009
10/01/2009
Change Order #1-9/09
AFFIDAVIT OF PUBLICATION
Account # 42742 AD# 255326
STATE OF WASHINGTON
COUNTY OF KITSAP
I, Laura Wessels, being first duly sworn on oath, deposes and says: That she is now, and at all times
embraced in the publication herein mentioned was the principal clerk of the printers and publishers of
KITSAP SUN; that said newspaper has been approved as a legal newspaper by order of the Superior Court
of the County of Kitsap, in which County it is published and is now and has been for more than six months
prior to the date of the publication hereinafter referred to, published in the English language continually as
a daily newspaper in Bremerton, Kitsap County, Washington, a weekly newspaper in Kitsap County,
Washington and is now and during all of said time, was printed in an office maintained in the aforesaid
place of publication of said newspaper; that the following is a true text of an advertisement as it was
published in regular issues (and not in supplement form) of said newspaper on the following date, to wit: A
November 25, 2009 and that such newspaper was regularly distributed to its subscribers during all of said
period. That the full amount of the fee charged for the foregoing publication is the sum 41.56. This
amount has not been paid in full.
4 ►►►►NUwiuhig
(Signature of Principal Clerk) S
.• M ••:'r_ v.
Subscribed and sworn to before me this day of December 4, 2009. ? . ` NOTj
Notary Public in and for the State of Washington, Kitsap County. Off: •
��n►n► ►N►
NOTICE OF COMPLETION
Notice of Completion has been issued to Unimark, Inc. for City Project No. 4403 and 4426, City Contract
No. 4782 for the Warehouse and Maintenance Building Additions. Any parties having a claim for material,
labor or damages related to this Contract have forty-five (45) days from the date of first publication of this
notice to file a claim.
Carol Etgen
City Clerk
345 6th Street
Bremerton, Washington 98337
November 25, 2009 ...................AD #20094760
CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 1
PROJECT NAME: Warehouse and Maintenance Building Additions
PROJECT NO:
4403 & 4426
CONTRACTOR: Unimark, Inc.
ORIGINAL CONTRACT AMOUNT:
$470,134.83 DAYS:
280.
PREVIOUSLY APPROVED CHANGES:
$0 DAYS:
o
($4,554) DAYS:
o
THIS CHANGE:
REVISED CONTRACT AMOUNT:
$465,580.83 DAYS:
o
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessary or required to complete the
Change Order Items. The increase or decrease in contract price shown below includes any applicable taxes.
DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT
0 ..-- CONTRACT CONTRACT TIME
r--- r--- AMOUNT AMOUNT EXTENSION
..--
Q) Q) ($) ($) (DAYS:)
:::l :::l
0::: 0:::
Modifications have been made in the construction of
these two additions. These modifications have been
done to better benefit the use of the structures. To
date, these modifications are:
Conflict with Existing Foundations - In excavating for
the new building footings, a conflict was found with the
existing footings along both building edges. This
tequired a significant modification to how the footings
were constructed with drilling and doweling being done
to graft the two foundations together. $2,805
Concrete Aprons - The contract documents show
asphalt being placed entirely up to the new building
footprint and the existing concrete aprons were
overlooked in the plans. The City deleted the restoration
work from the contract to allow City forces to complete ($12,052)
the aprons and finish the asphalt repairs.
Garage Doors - To provide better energy efficiency for
the structures, a proposal was requested to upgrade the
doors to insulated models. $1,380
Electric Heater in Warehouse Addition - The original
plans show an electric space heater to provide heat in
the working space in this addition. As the buildings are
currently served with gas and to decrease the electrical
demand from the addition, a proposal was requested to
CONTRACT CHANGE ORDER NO: 1
PROJECT NAME: Warehouse and Maintenance Building Additions
change the electric unit heater to gas.
$870
Hose Bib and Water Heater - With the addition of a
washing machine in the addition, the existing tank in the
warehouse is not sufficient to provide for the new
demand. A proposal was requested for the new tank
and to provide a hose bib on the exterior of the new
addition for the Sign Shops use.
$1,655
Wainscot in Maintenance Building Addition - The
contract documents show wainscot being installed on
the face of the existing building inside the addition. As
this is a block building, and it is unfaced in the existing
building, the City has chosen to delete this finish and
accept a credit to the contract.
($644 )
Exit a00r hl !"!!~ifltenance Building Addition .... The door '2"1:
the center of the east wall was found to be in conflict
with the structural components of the new addition.
The City has chosen to delete this door as this will allow
more room for storage and accept a credit to the
contract.
($1,213)
Window in Warehouse Building Addition - One of the
. windows located in the south wall of the addition was
found to be in conflict with structural components of the
new addition. The City has chosen to delete this
window and accept a credit to the contract.
($334 )
Upgrade to more Energy Efficient Fixtures - The
contract documents require the use of T-8 fixtures
throughout both additions. As part of the City's drive
to become more energy efficient, the new standards
require T-5 fixtures. A proposal was requested to
update the fixtures to meet the new City standards.
$2,979
NET CHANGE IN CONTRACT AMOUNT
INCREASE OR (DECREASE)
($4,554 )
o
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any
kind or nature arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, on-site or home office overhead, or lost profits.
Nothing in this Change Order shall limit the City's right to bring a claim for past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract
price specified for each item, including any and all supervision costs and other miscellaneous costs relating to
the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to
said Change Order.
This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that this Change Order shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a change order that is
binding on the parties of this contract. In addition, Contractor warrants that it has or will inform the surety of
this change, and shall take appropriate action to modify any bonds required under the contract to address this
change.
Page 2 of3
. , , t
CONTRACT CHANGE ORDER NO: 1
PROJECT NAME: Warehouse and Maintenance Building Additions
RECOMMENDED:
~G~
RECOMMENDED:
~~~~
3I[lEC: OF PUBLIC WORKS
CONTRACTOR
~ ,. /t?C--F /1/
~ M~/ :11 ~ rft-yt.~~vdq
MAYOR (
-r~sI09-
Date
c? 7//~$f
,/ D'8te
-=1 /~ /0'
Date
ACCEPTED:
APPROVED:
rz!t
ATTEST:
ci#d~
Page 3 of 3
Contract Number: 4782
Vendor: UNIMARK CONSTRUCTION GROUP LLC
Subject: Warehouse & Maintenance Building Additions - PW&U
Department: Engineering
File Class: LEG 12-1
Begin Date: 01/22/2009
End Date: 06/30/2009
Review Date: 06/01/2009
Vault Date:
Comments:
.,
CONTRACT
PUBLIC WORKS & UTILITIES
WAREHOUSE & MAINTENANCE BUILDING ADDITIONS
(Page 1 of 7)
:-n.
This agreement, made and entered into In triplicate, this 3~ day of
D~~~ ,2008 , by and between the City of Bremerton, hereinafter
called the City, and UN 1I~\^2 K ColIJSTl.uc:noL.J 6~oup LLc:.. , hereinafter called the
.
Contractor:
Witnesseth:
That in consideration of the terms and conditions contained herein and attached and made a
part of this agreement, the parties hereto covenant and agree as follows:
I. The Contractor shall perform all work and furnish all labor, tools, materials and
equipment for the Public Works & Utilities - Warehouse & Maintenance Additions.
All work to be in accordance with and as described in the attached Specifications,
Drawings, General Provisions, Special Provisions and the 2006 Standard Specifications
for Road, Bridge and Municipal Construction (English), which are by this reference
incorporated herein and made a part hereof, and shall perform any alterations in or
additions to the work provided under this Contract and every part thereof.
.. The Contractor shall begin the work within ten (10) calendar days after the date that
written NOTICE TO PROCEED is issued to the Contractor. The Contractor shall
complete the work no later than one hundred forty (140) calendar days after the date that
NOTICE TO PROCEED is issued. PA&T Or.JC t.JOT'IC. E '1b Pa.oiao'TO ee ':J:.!6uCO FoL
o ~ M~ B-J"-Ott.Jb PE.Su:,W AtlJO SuOc.o".''''EAc,:toL Su8iIll\11f1'\L.$. p^1tT TWO 1ooJ0'TIC.E TI> PRDeItlD
Tb O~ :a:~ED WrtlI Du'-CI...e:. ~,T ^""O COI'-"",ttI.)(..E ~~c,:nolJ CAl..&r.JO/I\I.
If said wor is not completed within the time specified, the Contractor agrees to pay to
the City an amount in accordance with Section 00100, Part 1-2.06(E) of these Contract
Documents for each calendar day said work remains incomplete after expiration of the
specified times as liquidated damages.
The Contractor shall provide and bear the expense of all equipment, tools, material and
labor of any sort whatsoever that may be required for the transfer of materials and for
construction and completing the work provided for in this Contract and every part
thereof, except such as are mentioned in the specifications to be furnished by the City.
II. The City hereby promises and agrees with the Contractor to employ and does employ
the Contractor to provide the materials and to do and cause to be done the above
described work to complete and finish the same according to the attached
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Forms
Page 00300 - 17
CONTRACT
(Page 2 of 7)
plans and specifications and the terms and conditions herein contained and hereby
contracts to pay for the same according to the attached specifications and the approved
bid as attached hereto incorporated by reference, at the time and in the manner and upon
the conditions provided for in this Contract.
III. The Contractor for himself/herself, and for his/her heirs, executors, administrators,
successors, and assigns, does hereby agree to fulfill the performance of all covenants
herein contained upon the part of the Contractor.
IV, It is further provided that no liability shall attach to the City of Bremerton by reason of
entering into this Contract, except as expressly provided herein.
V, INSURANCE AND INDEMNIFICATION
Insurance: The Contractor shall procure and maintain, during the term of construction
and throughout the specified term of maintenance, insurance of the types and in the
amounts described below against claims for injuries to persons or damage to property
which may arise from or in connection with the performance of the work here under by
the Contractor, its agents, representatives, employees, sub-consultants and! or
subcontractors. The Contractor shall not commence work until he has obtained and filed
with the City the bond referred to in Part 1-1.04(A) of these General Conditions and
Certificate of insurance for all insurance as required under the following sub-paragraphs,
and further until such insurance and bond have been approved.
Note: The Contractor's insurance shall be primary insurance with respect to the City
and non-contributory with respect to any insurance the City may have.
Before beginning work on this project described in this contract, the Contractor shall
provide a Certificate of Insurance evidencing:
1. Worker's Compensation and Employer's Liability Insurance
The contractor shall maintain worker's compensation insurance in the amount, and in
the terms, required by any applicable statutes for all employees engaged in work under
this contract.
If any such work is subcontracted, the Contractor shall require each Subcontractor
similarly provide workman's compensation insurance for all Subcontractor's employees
unless such employees are covered by the Contractor's worker's compensation
insurance. The Contractor shall provide and shall cause each Subcontractor to provide
adequate employer's liability insurance for the protection of any class of employee
engaged in hazardous work under this contract and not otherwise protected under
workman's compensation.
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Fonns
Page 00300 - 18
CONTRACT
(Page 3 of 7)
2. Public Liability Insurance
The Contractor shall obtain, and maintain during the life of this contract, public liability
insurance covering the Contractor and all Subcontractors.
All insurance shall name the City of Bremerton as additional insured at no additional
cost to the City,
The above insurance shall cover claims for damages for personal injury, wrongful death
and property damage, which may arise from operation under this contract, whether such
operations are performed by the Contractor, or by any Subcontractor or anyone directly
or indirectly employed by either.
In addition, the Contractor agrees to hold the City harmless and to defend and indemnify
the City from all expenses, claims or losses occasioned through the performance of this
contract by the Contractor, any Subcontractor, or persons working directly or indirectly
for the Contractor.
Contractor and Subcontractor Insurance
The Contractor shall not commence work under this Contract until they have obtained
all the insurance required hereunder and such insurance has been reviewed and approved
by the City's Risk Manager, nor shall the Contractor allow any Subcontractor to
commence work on this subcontract until insurance specified below has been obtained.
Review of the insurance by the City shall not relieve or decrease the liability of the
Contractor hereunder.
General Liability Insurance (lncludine: Automobile)
The Contractor shall maintain during the life of this Contract such general liability,
completed operations and products liability, and automobile liability insurance as will
provide coverage for property damages for personal injury, including accidental death,
as well as for claims for property damage, which may arise directly or indirectly from
performance of the work under this Contract. The general liability policy shall include
contractual liability assumed by the Contractor under Part 1-1.04(B)3.,
"Indemnification". Coverage for property damage shall be on a "broad form" basis with
no exclusions for "X, C & D". The amount of insurance shall not be less than
$1,000,000 per occurrence. The Contractor shall further maintain Excess Liability
insurance with limits not less than $1,000,000 per occurrence and aggregate.
In the event any work under this Contract is performed by the Subcontractor, the
Contractor shall be responsible for any liability directly or indirectly arising out of the
work performed by the Subcontractor, to the extent such liability is not covered by the
Subcontractor's insurance.
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Fonns
Page 00300 - 19
CONTRACT
(Page 4 of 7)
The City of Bremerton, their officers, agents, and employees shall be named as
Additional Insured's on the Contractor's and subcontractor's general liability and
automobile liability insurance policies for any claims arising out of work performed
under this Contract.
3. Builder's All Risk Insurance
Unless otherwise modified, the Contractor shall secure and maintain during the life of
the Contract, Builder's All risk Insurance coverage in an amount equal to the full value
of the contract under construction. Such insurance shall include coverage for
earthquake, landslide, flood, collapse, loss due to the result of faulty workmanship, and
all other normally covered risks, and shall provide for losses to be paid to the Contractor,
City, and Architect as their interest may appear.
Indemnification
The Contractor agrees to defend, indemnify, and hold the City, its officers, officials,
employees, agents, volunteers, and assigns harmless from any and all claims, injuries,
damages, losses or suits, including all legal costs and attorney fees, arising out of or in
conjunction with the performance of this contract, except for injuries and damages
caused by the sole negligence of the City,
The City's inspection or acceptance of any of the Contractor's work when completed
shall not be grounds to avoid any of these covenants of indemnification.
Should a court of competent jurisdiction determine that this contract is subject to RCW
4.24.115, then, in the event of liability for damages arising out of bodily injury to
persons or damages to property caused by or resulting from the concurrent negligence of
the Contractor and the City, its officers, officials, employees, agents and volunteers, the
Contractor's liability hereunder shall be only to the extent of the Contractor's
negligence,
IT IS FURTHER SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THE
INDEMNIFICATION PROVIDED HEREIN CONSTITUTES THE
CONTRACTOR'S WAIVER OF IMMUNITY UNDER INDUSTRIAL INSURANCE,
TITLE 51 RCW, SOLELY FOR THE PURPOSES OF THIS INDEMNIFICATION.
THE PARTIES FURTHER ACKNOWLEDGE THAT THEY HAVE MUTUALLY
NEGOTIATED THIS WAIVER.
The provisions of this section shall survive the expiration or termination of this contract.
VI. GENERAL CONDITIONS
A. Report and Information: When requested by the City, Contractor shall furnish
periodic reports and documents on matters covered by this Contract. The reports
and documents shall be furnished in the time and form requested. Contractor shall
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Forms
Page 00300 - 20
CONTRACT
(Page 5 of 7)
maintain accounting records in accordance with Generally Accepted Accounting
Principles (GAAP) to substantiate all billed amounts.
B. Entire Contract: This Contract constitute the entire agreement between the Parties,
and the Parties acknowledge that there are no other agreements, written or oral that
have not been set forth in the text of this contract. The section headings and article
titles of this Contract shall have no effect upon the construction or interpretation of
any part hereof.
C. Severability: Should any part of this Contract be found void, the balance of the
Agreement shall remain in full force and effect.
D. Modification: This Contract may only be modified by written instrument signed by
both Parties.
E. Waiver: Failure to enforce any provision of this Contract shall not be deemed a
waiver of that provision. Waiver of any right or power arising out of this Agreement
shall not be deemed waiver of any other right or power.
F. Compliance with Laws: Contractor shall comply with all applicable Federal, State
and local laws in performing its obligation under this Contract.
G. Choice of Law and Venue: This Contract shall be interpreted according to the laws
of the State of Washington. Any judicial action to resolve disputes arising out of
this Contract shall be brought in Kitsap County.
VII. WARRANTY
The Contractor shall warrant the work for a period of one (1) year as referenced in the
General Conditions, If the Contractor does not accomplish the corrections within a
reasonable time, the City may complete the correction and the Contractor shall pay all
costs by the City in order to accomplish the correction.
XI. TERMINATION
The City may terminate this Contract without notice for good cause. "Good Cause"
shall include, without limitation, anyone or more of the following events:
A. The Contractor's failure to supply sufficient skilled workers or suitable materials or
equipment.
B. The Contractor's failure to prosecute the work with such diligence as will ensure its
physical completion within the original physical completion time specified in this
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Foons
Page 00300 - 21
CONTRACT
(Page 6 of 7)
Agreement and any extensions of time which may have been granted to the
Contractor by change order or otherwise.
C. The Contractor's failure to make full and prompt payment to subcontractors or for
material or labor.
D. The Contractor's disregard of federal, state or local laws, rules or regulations.
E. The Contractor's filing for bankruptcy or becoming adjudged bankrupt.
F, The Contractor disregards the authority of the City.
G. The Contractor performs work which deviates from the Contract, and neglects or
refuses to correct rejected work.
H. The Contractor's failure to provide continuous competent supervision.
1. The Contractor Otherwise violates in any material way any provisions or
requirements of the Contract.
If the City terminates this Contract for good cause, the Contractor shall not receive any monies due
under this Contract, if any, until the Contract work is completed.
In witness whereof the parties hereto have caused this agreement to be executed the day and year
first herein above written.
CITY OF BREMERTON CONTRACTOR
~f$~ UNIMI'\e.1( Coto.JSTtoCT'IO\J (it,oup Lt..c..
,
-fov- Mayor
By: ~ ~~
Title: {'Ii rte &of 7' tll't. 1/. fJw
Date: '/7/0'
{
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Forms
Page 00300 - 22
CONTRACT
(Page 7 of 7)
ATTEST:
rk1~~Ml)
City Cler
APPROVED:
~~~~~ ~-
Ci ~ -
4403 - BREMERTON-WAREHOUSE & MAINTENANCE BUILDING ADDITIONS Bidders Checklist & Bid/Contract Forms
Page 00300 - 23