DATE SUBMITTED: August 15,2007
AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
ff/ft3D7- ;<'07
........................................................................................
SUBJECT: Award Contract for Sewage
Pump Station CW-1 Upgrade to Stan Palmer
Construction.
Committee Meeting Date: August 22, 2007
COUNCIL MEETING Date: September 5, 2007
Department: PW&U, Engineering
Presenter: Michael Mecham
Phone: 473-5288
SUMMARY: Sealed bids for construction of the project titled "Sewage Pump Station CW-1
Upgrade" were opened on August 14,2007. The engineer's estimate for construction of the project is
$1,373,000. Three bids were received for this project. Stan Palmer Construction was the lowest
responsive, responsible bidder with a bid of $1,448,724 (including sales tax). The City is exercising
its right to delete Bid Item #1 (Temporary Bypass Pumping for $165,000) from the contract. The
revised contract amount is $1,269,534 (including sales tax).
ATTACHMENTS: 1. Council Summary; 2. Site and Vicinity Map; 3. Bid Tabulation
FISCAL IMPACTS: Construction of this project is funded by loans from the Washington State
Public Works Board (PWTF loan program) and utility rates. The loans are PWTF Loan #03-291-004
for $475,000 and PWTF Loan # 07-962-004 for $675,000. This project is included in the CIP and the
2007 budget. The 2007 budget for this project is $675,000; the anticipated 2007 costs are $550,000.
APPROVALS:
DEPARTMENT DIRECTOR:
CITY ATTORNEY:
FINANCE DIRECTOR:
MA YOR:
HSCAL/DUDOET.-
.QPERATIOt;S. f(,.j
COUNCIL PRESIDENT:
I CONSENT AGENDA [;(I.]
COUNCIL ACTION: ~prove
o Deny
o Table
o Continue 0 No Action