CITY COUNCIL
.......................................................D................................
SUBJECT: State Participating Agreement
with WSDOT for Hot Mix Asphalt Overlay
ofSR 3 On-Ramp
Committee Meeting Date: April 11, 2007
COUNCIL MEETING Date: April 18, 2007
Department: PW&U, Engineering
Presenter: Michael Mecham
Phone: 473-5288
SUMMARY: The City of Bremerton and WSDOT seek additional work for incorporation into the
SR 304 Transportation Improvement Project (TIP), Navy Yard Highway Phase. This work consists of
incorporating additional paving area at the SR304/SR 3 interchange, which would be outside of the
current project limits.
ATTACHMENTS: 1. Council Summary; 2. Aerial Photograph Exhibit; 3. State Participating
Agreement with WSDOT
FISCAL IMP ACTS (Include Budgeted Amount): The approximate cost for the additional work is
$63,300 and will be fully reimbursed by WSDOT.
APPROVALS:
DEP ARTMENT DIRECTO
CITY ATTORNEY:
FINANCE DIRECTOR:
MA YOR:
COMMITTEE CHAIR
COUNCIL PRESIDENT:
~~
. ~ --:-, .
CONSENT AGENDA
GENERAL BUSINESS 0
PUBLIC HEARING 0
RECOMMENDED MOTION: Move to approve State Participating Agreement No. GCA 5178 with
the Washington State Department of Transportation and authorize the Mayor to finalize and execute
the necessary contract documents for the agreement in substantially the same terms and conditions as
presented.
COUNCIL ACTION: ~prove 0 Deny