RESOLUTION NO. 468
~, A. L. Rockwell, General Contractor flor Flr~ Alar~
System, Project Wash° 45og6?-CN, B~emerton, Wash. has requested
an extension of time of completion of said contract from Sept.
~, 1945 to December g, 1945 or 90 days.
WH~AS, the over mm in the specified contract completion
tl~e is due .entirely to the supplier of certain equApment bela6
unable to make shipment before late in October, as described in
Contractorts lett®r of August 24, 1945.
AND ~EAS, liquidated damages were not specified in the
Contract,
AND~HEREAS, No dam~e of any nature whatsoever occurred by
reason of failume of the Contractor to complete his work within
the time specified.
NOW, THEREFORE, BE IT RESOLVED
(1) That no liquidated damages be asserted by reason off A. L,
Rockwell's failure to complete the work within the time
specified, and
(g) That the resolution of unqualified, unconditional
waiving of damages be transmitted to the Resional
Engineer of the Fedel~l Works Agency for his approval,
Passed by the City Council of the City of B~emer~on, Washln~ton,
si~ned by the Mayor, and attested by the City Cler~ in authen-
tication of such passage this 29th day of August, 1945.