WHEREAS, there has been submitted to the City Council of
the City of Bremerton change order No. i on the West Bremerton
sewage traatment plant, Unit No. II, which has been approved by
the City Council, and
WHEREAS, d~ange order No. i will necessarily extend the
completion date of said project for a period of seven days, and
WHEREAS, liquid,ted d~mages are specified by said contract
but it appears that no damage of any nature will occur by reason
of the failure of the contracter to complete its work within the
time specified by the contract and that said change order No. 1
is reasonable and necessary; now, therefore,
BE IT RESOLVED:
1. That Hall-Atwater Company, contractors, be granted an
extension of seven days within which to complete the work required
by its contract.
2. That no liquidated damages be claimed by the City by
reason of the failure of the contractor to complete within the
time specified by the original contract.
3. That a copy of this resolution be forwarded to the
~Hall-Atwater Company and to the sure~y on the contractor's per-
forman ce bond.
Passed by the City Council of the City of Bremerton, signed
by the Acting Mayor and attested by the City Clerk in authentication
of such passage this l~th day of December, 1949.
ATTEST: ~ Acting Mayor,
LULU
D.
HADDON
E.H.T.McGOWAN, City Clerk