HomeMy WebLinkAbout699 WHEREAS, a request has been received from Hoaglund-
Findlay Engineering Company for an extension of time within
which to complete its contract with the City of Bremerton
for a sewage treatment plant, pressure llft stations and ap-
purtenances, to commence at the end of the agreed contract
time limit; and
WHEREAS, the date specified for the completion of the
work is May SO, 1949, which date has been extended for an
additional sixty days pursuant to resolution of the City
Council dated June 8, 1949; and
WHEREAS, the overrun in the specified contract completion
time is due to th~,contractor'sfnability to obtain equipment
necessar~ to complete said project; and
WHEREAS, liquidated damages are specified by said contract
but it appears that no damage of any nature whatsoever will
occur by reason of the failure of the contractor to complete
its work within the time specified;
NOW, THEREFORE, BE IT RESOLVED:
1. That Hoaglund-Findlay Engineering Company be granted an
additional extension of one hundred and twenty days within which
to complete the work required by its contract.
2. That no liquidated damages be claimed by the City of
Bremerton by reason of the failure of Hoaglund-Findlay Engineer-
/ing Company to complete its work within the date
specified.
~-- -- 5. That a copy of this resolution be sent to the cont:aator
and the surety on the contractor's performance bond.
Passed by the City Council of the City of Bremerton, signed
by the Mayor and attested by the City Clerk in authentication of
such passage this 27th day of July, 1949.