HomeMy WebLinkAbout741 RESOLUTI ON NO.
WHEREAS, heretofore the City of Bremerton, a municipal
corporation, and Hall-Atwater Company entered into a certain contract
for the erection, cons~;ruction aad completion of the West Bremerton
Sewage Treatment Plant and Pump Station~ and
~.fHEREAS, said Hall-Atwater Company, has requested in
writing~ an extension of sixty (60) days upon its contract by
letter dated July 7, 1950, and
'.,~i~REAS, certain weather conditions and authorized changed
orders have prevented the completion of the work contemplated by
said con[~ract at the time set the?ein and that none of the conditions
were within the control of the Hal].-gtwater Company and the Consul-
uing Engineer and City Engineer have recom~uea~]ed the extension of
time, and
?[HE'!EAS, liquidated damages are specified by said contract,
but it appears that no dama[~e of' any nature will occur by ueason
of the failu e of Hall-Atwater Company, as contractor, to complete
the work within the 'time specified by the contract and that any
damages have been waived by the contractor;
NOW, TI{E~ii'O~{E, BE IT RESOLVED:
1o That Hall-Atwa.ter Company, contractors, be granted an
extensio~ of sixty (60) days within which to complete the work
required by its contract with the City of Bremerton in accordance
with the request and extension contained in the letter dated July
7, 1950.
2. That no liquidated da;,~a£es be claimed by the City of
Bremerton by reason of th? failure of the conloractor to complete its
contract within the ~ime specified by the original contract and the
contractor has waived any claim for damages by reason of such ex-
tension of completion date.
3, That a copy of this resolution be forwarde~ by the
City Clerk to Halt-Atwater Company ,and to the surety on the
contractor's peI~ormanc~ oondo
PASSED unanimously by the City Council of theCity of
Bremerton, signed by the ~'~ayor and attested by the City Clerk
in authentication of such passage, this 12th day of July, 195Oo
AT I'EST:
E.HoT. )(~-~o~an, City Clerk