HomeMy WebLinkAbout726 RE~OLUTION NO. 7~~
'*q~EREAS, heretofore the City of Bremerton and Hall-Atwater
Company entered into a contract for the erection, construction and
completion of the West Bremerton Sewage Treatment Plant and Pump
Station, and ~fHE~AS, there has been submitted to the City Council
of the City of B remerton Change Order No. 2 on said contract, and
?~ERELS, Change Order No. 2 will necessarily extend the completion
date of said project for a period of thirty-five (35) days and
will cost an additional ~6,763.75, and ~i'~HEREA$~ liquidated damages
are specified by said contract, but it appears that no damage of
any nature will occur by reason of the failure of the contractor to
complete its work within the time specified by the contract and
that damages are waived by the contractor;
NOW, THEREFORE, BE IT RESOLVED:
1. That Hall-Atwater Company, contractors, be granted
an extension of thirty-five (~5) days within which to complete
the work required by its contract.
2. That no liquidated damages be claimed by the City
by reason of the failure of the contractor to complete within the
time specified by the original contract and the contractor waives
any claim for dm~ages by reason of such change order.
~. That a copy of this resolution be forwarded to the
Hall-Atwater Company and to the s~rety on the contractor's per-
formance bond.
PASSED unanimously by the City Council of the City of
Bremer%on, signed by the l~layor and attested by the City Clerk
in authentication of such passage, this 1st day of February,
AT TInS T:
E.H.T. McGowan, City Clerk.