Loading...
HomeMy WebLinkAbout726 RE~OLUTION NO. 7~~ '*q~EREAS, heretofore the City of Bremerton and Hall-Atwater Company entered into a contract for the erection, construction and completion of the West Bremerton Sewage Treatment Plant and Pump Station, and ~fHE~AS, there has been submitted to the City Council of the City of B remerton Change Order No. 2 on said contract, and ?~ERELS, Change Order No. 2 will necessarily extend the completion date of said project for a period of thirty-five (35) days and will cost an additional ~6,763.75, and ~i'~HEREA$~ liquidated damages are specified by said contract, but it appears that no damage of any nature will occur by reason of the failure of the contractor to complete its work within the time specified by the contract and that damages are waived by the contractor; NOW, THEREFORE, BE IT RESOLVED: 1. That Hall-Atwater Company, contractors, be granted an extension of thirty-five (~5) days within which to complete the work required by its contract. 2. That no liquidated damages be claimed by the City by reason of the failure of the contractor to complete within the time specified by the original contract and the contractor waives any claim for dm~ages by reason of such change order. ~. That a copy of this resolution be forwarded to the Hall-Atwater Company and to the s~rety on the contractor's per- formance bond. PASSED unanimously by the City Council of the City of Bremer%on, signed by the l~layor and attested by the City Clerk in authentication of such passage, this 1st day of February, AT TInS T: E.H.T. McGowan, City Clerk.