HomeMy WebLinkAbout799 RESOLUTION NO. 7~9
WHEREAS, heretofore, the City of Bremerton entered into a
L ~' ~ '/certain contract with JOE ~VERY for the doing of certain work upon
· ~ Winfield and Trent'on Avenues in the City of Bremerton, Washington,
which said work was to have been completed by the 26th day of April,
1952, in accordance with the terms of said contract, and
WHEREAS, at the request of the Engineering Department of
the City of Bremerton, the contractor delayed commencement of said
work, awaiting better weather, and
V~LEREAS, by reason of said delay in commencing said work it
has become impossible to finish the said work by the 26th day of
April, 1952, and that it will be necessary that an extension of
thirty {30) days be given the contractor in order to complete said
work, and
WHEREAS, no liquidated damages are specified in the said
contract and no damages of any nature will occur by reason of the
failure of the contractor to complete by the date set in the con-
trac~ as of April 26, 1952~
NOW, THEREFORE, BE iT RESOLVEDby the City Council of the
City of Bremerton that the time of completion for the work contem-
plated under said co~ract with Joe Avery be and hereby is changed
to and extended for a period of thirty (30) days to the 26th day of
YL~y, 1952, for completion, and
BE IT FURTHER RESOLVED that no liquidated damages or damages
of any kind or nature shall be asserted by the City of Bremerton by
reason of the contractor's failure to complete by the date set forth
in the contract, and
BE IT FURTHER RESOLVED that copies of this Resolution be for-
warded by the City Clerk to Joe Avery, the contractor, and the surety
on his performance bond filed with t he City.
PASSED by the City Council of the City of Bremerton, signed
by the Mayor and attested by the City Clerk in authentication of
such passage this 7th day o£ May, 1952.
L. "HUM" KEAN, Mayor
Attest:
E. H. T. MC GOWAN, City Clerk