HomeMy WebLinkAbout867 RESOLUTION NO. __~_~_~ ....
WHEREAS, heretofore and on the 27th day of NoYember, 1953,
the City of Bremerton entered into a certain contract with Ted
Hyde, d/b/a Hyde Construction Company, for the erection and con-
struction of the Forest Ridge Reservoir in the City of Bremerton,
Washington, and under which contract said work was to have been
completed within one hundred fifty (150) days from the date there-
of, and
WHEREAS, heretofore and on the 26th day of May, 195~, an
extension was given to said Ted Hyde to the 27th day of July,
195g, on the basis of unavoidable delay and weather conditions and
WHEREAS, by reason of the use of increased qualities of
material being from an estimated one thousand four hundred fifty
yards of concrete to an estimated two thousand one hundred yards
i'or Final completion, and for steel, one hundred sixty-eight
thousand oounds increased to two hundred and forty thousand pounds
that it will not be possible to com. Dlete said reservoir by the 27th
day of July, 195&,
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Bremerton that the time of completion for the work contem-
~lated under said described Contract be, and hereby is extended to
October 30th, 195~.
BE IT FURTHER RESOLVED that no liquidated damages or dam-
a,~es of any kind or nature shall be asserted by the City of Brem-
erton against said contractor for failure to complete by the
contract date, or any extension thereof, and
BE IT FURTHER RESOLVED that copies of this resolution be
~orwarded by the City Clerk to Ted Hyde, d/b/a Hyde Construction
Company, the contractor, and the surety on his performance bond
filed with the City.
PASSED by the City Council of the City of Bremerton, signed
by the Mayor and attested by the City Clerk in authentication of
such passage this 28th day of July, 195~. ~[,k~? /~ __
....E. H~ T-. ~C GOWAN, Ci~y'~ ~erk. -S. W. YOW~LL, Mayor.