HomeMy WebLinkAbout2289 RESOLUTION NO. 2289
A RESOLUTION REGARDING DEVELOPMENT SCHEDULE FOR
CENTRAL BUSINESS DISTRICT WATERFRONT
WHEREAS, the CIty of Bremerton expects to be offered the United
States Navy display vessel Turner Joy and expects this vessel to
be available for display in the second half of 19907 and
WHEREAS, it is imperative that adequate public access be in place
upon the vessel's arrival; and
WHEREAS, construction of a over-water park facility after upland
development would risk construction damage to the upland
development; and
WHEREAS, the Port of Bremerton is projecting a 1990 completion of
a transient marina facility which requires access to the shore at
the site of the proposed over-water park; and
WHEREAS, the estimated cost of construction of a over-water park
between first and second streets is in the neighborhood of
$400,000.00; and
WHEREAS, the City has secured funding in the amount of $309,000.00
to develop an over-water park; and
WHEREAS, the Puget Sound Naval Shipyard Centennial Committee is
embarking upon a fund raising project to develop Puget Sound Naval
Shipyard Centennial Plaza along the Central Business District
waterfront; and
WHEREAS, the Bremerton City Council approved a Special Use Permit
for expansion and upgrade of the parking lot at the Bremerton
Lumber site; and
WHEREAS, Bremer's Inc. has agreed to provide a landscape buffer
abutting park areas and removal of the Bremerton Lumber building.
NOW THEREFORE, BE IT RESOLVED THAT THE BREMERTON CITY COUNCIL:
Does hereby approve the following phased City managed/funded
construction schedule for 1990:
1. Over-Water Park between First and Second Streets;
2. Inner Harbor Park;
Puget Sound Naval Shipyard Centennial Plaza - eastern
terminus of Second Street right-of-way; and
BE IT FURTHER RESOLVED THAT THE BREMERTON CITY COUNCIL:
Does authorize the Mayor to negotiate a design contract with The
Portico Group to develop construction documents for the following
projects:
1. Over-water park and Turner Joy access facility from
First Street to the Turner Joy moorage site;
2.Inner Harbor Park;
Puget Sound Naval Shipyard Centennial Plaza on the eastern
terminus of Second Street right-of-way;
3.Ferry Terminal Park;
4.Point Turner beach access trail;
BE IT FURTHER RESOLVED THAT THE BREMERTON CITY COUNCIL:
Does request the Mayor to provide budget amendments to provide
funding the following construction projects:
1. Over-water Park between First and Second - full funding;
2. Inner Harbor Park;
Puget Sound Naval Shipyard Centennial Plaza -
identification of balance of funds necessary to complete
the project, assuming Puget Sound Naval Shipyard
participation;
3. Point Turner Beach Access;
4. Ferry Terminal Park
NOW THEREFORE BE IT RESOLVED: the completion of the above
expansion, demolition and landscaping will coincide with the
completion of the inner harbor park and the completion of the over-
water park.
PASSED by the Bremerton City Council this 7th day of
March, 1990.
Lynn Horton, President
APPROVEd this 9 day of March, 1990.
Louis Mentor, Mayor
ATTEST:
Kathleen McCluskey, City Clerk