HomeMy WebLinkAbout2726 RESOLUTION NO. 2726
2000 - 2005 SIX-YEAR TRANSPORTATION IMPROVEMENT PLAN
WHEREAS, THE CITY OF BREMERTON, has reviewed the work accomplished under
its Comprehensive Arterial Street Construction Program and determined current City Street Needs;
and,
WHEREAS, the City Council caused to be prepared a revised and extended Six-year
Transportation Improvement Plan for the period of January 1, 2000, to December 31, 2005, and
after public heating thereon approved the same;
NOW, THEREFORE, BE IT RESOLVED, that the revised and extended Six-Year
Transportation Improvement Plan 2000-2005 attached hereto as Exhibit A and Schedule is hereby
adopted as the revised and extended Six-year Transportation Improvement Plan for the period of
January 1, 2000, to December 31, 2005.
PASSED by the City Council of the City of Bremerton this 29th day of
,1999.
MIKE SHEPHERD, Council President
Supporting Information for the STIP 2000
1. SR 303 Major Investment Stud>.- WSDOT is managing the study, in coordination
with Bremerton. Kitsap Countv and Kitsap Transit. WSDOT selected a consultant
(Parametrix) to do the stud>. and they are currently working on the Statement of
Work. City of Bremerton and Kitsap County share of funds provided by an allocation
of Countywide TEA 21 funds. A presentation to the City Council on the scope of
work is scheduled for the study session of October 6. 1999.
2. SR3/SR304 Gorst to Bremerton Ferry Terminal - Burwell Street from Pacific Ave. to
Montgomery Ave. completed in 1999. The Gate Stage Improvements. from Porter St
and Cambrian Ave to Burw'ell St and Montgomery Ave., are expected to begin
construction in 2000 and be completed in 2001. The Naval Yard Highway Stage and
Ferry Terminal Stage are estimated to be completed in 2002.
Previous 2000 2001 2002 2003-5
Year
Design & $14,427,000 $7,195,000 $2,462,000
ROW
Construction $1,386,000 $5,346,000 $2,411,000 $3,617,000
$8,800.000 in funds is in jeopardy pending the outcome ofi-695. $7,800,000 of these
funds is from WSDOT and was approved by the State Legislature as part of the Ref.
49 funds. The other $1,000,000 would come from the Central Puget Sound Public
Transportation Account, which is also supported by MVET funds. Loss of these
funds w'ill not effect the Gateway Stage Improvements but would impact the
completion of the other stages.
3. West Hills Improvements - Received increased funding from Countywide TEA 21
allocation or $1.025 million. This combines with UATA, EDA and Arterial Street
funds for a total project budget of $3 million. Construction planned for 2000.
4. Auto Center Way Improvements - Bruen Ave. to SR 3 on-ramp - no changes. City
will develop a preliminary plan and cost estimate to use in obtaining funding.
5. Arsenal Way/Patton Ave Improvements - No changes
6. Miscellaneous (Local Program Support) - No changes. Used for arterial street
overlays. signal upgrades, signage, and miscellaneous work on the arterial street
system.
7. Construct Warren Avenue Off Ramp - Delayed until we can get funding.