HomeMy WebLinkAbout2399Kitsap-Rremerton Transmission Line
Kitsap County, Washington Contract No.
Tract PB-12RA
CITY OF BR~2~RTON
STATE OF WASHINGTON
AN ORDINANCE of the City of Bremerton, State of Washington, grant-
ing to the United States of America the right ko construct, operate and main-'
tain an electric power transmission line over and across Union Avenue, a
public street within the corporate limits of the City of Bremerton, Kitsap
County, State of Washington.
BE IT ORDAINED by the City Commission of the City of Bremerton,
State of Washington:
Section 1.' The Oity of Bremerton, State of Washington, does
hereby grant to the United States of America, Dep~rtment of the Interior,
acting through the Bonneville Power Administrator, Portland, Oregon, the
right to construct, operate and maintain for a period of fifty (50) years
the Bonneville Power Administration Kitsap-Bremerton transmission line over
and across Union Avenue, a public street in the City of Bremerton, the center
line of the transmission line crossing the center line of Union Avenue at
transmission line s~:~-ey station 68 + 80 in the S~NE~ of Section 21, Town-
ship 24 North, Range 1 East of the Willamette Meridian, and said transmission
line encroaching on the right-of-way for Union Avenue from opposite trans-
mission line survey station 75 + 70 to opposite transmission lime survey
station 74 + 20 in the NE~!~E~ of said Section 21, as shown on drawing Serial
No. 106320 prepared by the Bonneville Power Administration, United States
Department of the Interior, and on file in the office of the C~issioner of
Public Works of said City of Bremer%on.
Section 2. Ail costs of construction, operation, maintenance,
repair, relocation or removal of said transmission line shall be borne by
the United States of _America, and all construction, operation and mainte-
nance of said tran~ission line shall be performed in accordance with all
applicable laws and the specifications, rules and regulations set forth in
the latest editions of and supplements to the National Electrical ~afety
Code promulgated by the United States Bureau of Steax~ards.
Section 3. Any and all damage or injury necessarily done to
the City' s right-of-way or facilities or any property lawfully upon said
right-of-way in the construction, operation and maintenance of said trans-
mission line shall be immediately repaired or reconstructed by the United
States of America, under the supervision and to the satisfaction of the
Commissioner of Public Works of said City of Bremerton. Upon the failure,
neglect or refusal of the United States of America to do and perform
immediately any repairs or reconstruction of said right-of-way, facilities
or other property herein required of the U~ited States of America, the City
of Bremerton may undertake and perform such repairs or reconstruction and
the cost thereof will be paid by the United States of America upon presen-
tation of properly executed vouchers therefor; provided, however, that the
City of Bremerton shall submit an estimate of the cost of said repairs or
reconstruction t° the United States of America through the Bonneville Power
Administrator, Portland, Oregon, and shall obtain his approval thereof
before making such repairs or performing such reconstruction. If in an
emergency, the existence of which shall be determined by the City of
Bremerton, it becomes necessary for the City of Bremerton to make such
repairs or perform such reconstruction without first having thus obtained
the approval of the United States of America, the latter shall not be re-
quired to make any payment therefor unless the sums expended or any lesser
sums shall be later approved by the United States of America.
Section 4. Any breach of any of the conditions and requirements
made in this ordinance, or failure on the part of the United States to pro-
ceed with due diligence and in good faith with the construction work to be
done hereunder, shall subject 'the rights granted herein to cancellation
after a hearing before the City Commission of said City of Bremerton, of
which said hearing the United States through said Bonneville Power Adminis-
trator shall be given at least ten (10) days' written notice at the prin-
cipal office of the Bonneville Power Administration at Portland, Oregon,
otherwise by publishing a notice of said hearing once a week for two (2)
successive weeks in a newspaper of general circulation in Kitsap County,
'Washington, the last publication to be at least ten (10) days before the
date fixed for said hearing.
2
Section 5. The United States of America, Department of the
Interior, acting through the Bonneville Power Administrator, Portland,
Oregon, shall within twenty (20) days from receipt of a certified copy
of this ordinance file with the City Commission of the City of Bremerton,
Washington, its written acceptance of the terms and conditions of this
ordinance.
Section 6. All expenditures, to be made by the United States
of America under the provisions of this ordinance shall be subject to
appropriations being available for the purpoe.
APPROVED on first reading this 15th day of June, 1960.
PASSED by the City Council of the City of Bremerton, signed
by the Mayor and attested by the City Clerk in authentication of such
passage this 22nd day of June, 1960.
H. O. DOMSTAD, Mayor
(SEAL)
ATTEST:
E. H. T. McGOh~N, City Clerk
ApprQ~ as to Fgr~:
C it: ~r ~e~ ,~rBr '~ ' Wa shingt on
STATE ~ WASHINGTON
) Sec
County of Kitsap )
I, E. H. T. McGOWAN, City Clerk of the City of Bremerton,
Kitsap County, Washington, hereby certify that the foregoing is a
full, true and correct copy of Ordinance No. FJ.~;~? , passed by the
Commission of the City of Bremerton, State of WaShington, on this
22nd day of June, 1960.
WITNESS MY HAND AND SEAL of said City of Bremerton this
22nd day of June, 1960.
E. ~' T-, ~GOWAN, City Clerk