HomeMy WebLinkAbout03-154DATE SUBMITTED: August 6, 2003 BILL # 03 - / $4
AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Committee Meeting Date: August 12, 2003
CONTRACT CHANGE ORDER- COUNCIL MEETING
Associated Underwater Services Inc.- Date: August 20, 2003
Bonding of Steel Piles to Complete the Department: Parks & Recreation
Cathodic Protection of Steel Piles Presenter: Jim Spencer, Director
Phone: 473-7252
SUMMARY: This Change Order is necessary to install pile-to-pile bonding of the steel piles at the
Boardwalk. The additional cost to bond 131-steel piles to each other is $ 41,257.13 including tax.
On July 28, 2003, a/ter cathodic protection had been in operation for a week, the Boardwalk's original
pile-to-pile bonding system could be tested, as a part of the cathodic protection system testing
protocol. During this testing, it was determined that the pile-to-pile bonding system is non-existent.
ATTACHMENTS: Associated Underwater Services, Inc. Lump Sum Cost Proposal, dated August
5, 2003.
FISCAL IMPACTS (Include Budgeted Amount): The installation will allow proper operation of the
in-progress Cathodic Protection system and pile wrap installation, and increase grounding safety to
City personnel and the g~neral public. The additional lump sum cost of this Change Order is within
the executed contract between the State of Washington Department of Community, Trade and
Economic Developmem (CTED) and the City of Bremerton.
APPROVALS:
DEPARTMENT DIRECTOR:
CITY ATTORNEY:
FISCAL/BUDGET:COUNCILOPERATIONS: PRESIDENT:
RECOMMENDED MOTION: That the City Council approve this Change Order to Associated
Underwater Services, Inc., in the amount of $41,257.13 and authorize the Mayor to finalize and
execute the Change Order in substantially the same form as attached.