HomeMy WebLinkAbout02-228 AGENDA BILL BREMERTON CITY COUNCIL 1. SUBJECT: CONTRACT AWARD FOR FOR AGENDA OF: November 20, 2002 SEWAGE PUMP STATION EB-2. ORIGINATING DEPT: PW&U Engineering Division ORIGINATOR: W. Eugene Sampley, Direc}~r?'~ DATE SUBMITTED: November 7, 2002 2. CLEARANCES: (comment on back ifnec_ess~ary)~J~ ~.~. ~E~XHIBITS Director, Public Works/Utilities ~t ~ J~'- A. Bid Tabulation Form City Attorney ~ ": ~ ' -~-~..~ B. Site Map Purchasing Manager Council Budget & Finance Committee Council Operations Committee ENDORS~ ~TION APPROVED BY COUNCIL PRESIDENT FOR SUBMITTAL: MAYOI~"-~-- ~'t,'JED "- 4. SUMMARY STATEMENT AND REQUIREMENT FOR COUNCIL ACTION: Modifications to Sewage Pump Station EB-2 are required for the Trenton/Cherry CSO reduction improvements set forth in the City's CSO Reduction Plan and required for compliance with the PSA Consent Decree. Bids were opened for the Sewage Pump Station EB-2 2002 Modifications project on November 8, 2002. There were 2 bids received for this proj ect. Stan Palmer Construction was the lowest responsive bidder with a bid of $1,674,242.50. The Engineer's estimate for the project was a range of $1,600,000 to $1,900,000, including applicable taxes. The requested action before the City Council is approval of the contract with Stan Palmer Construction for construction of the Sewage Pump Station EB-2 2002 Modifications project. 5. RECOMMENDATION: The City Council approve award of the Sewage Pump Station EB-2 2002 Modifications project to Stan Palmer Construction, for the amount of $1,674,242.50, including applicable taxes and authorize the Mayor to execute the same. 9. RESPONSIBLE OFFICIAL: City Engineer ENFORCEMENT OFFICIAL: N/A EXPIRATION DATE: REVIEW DATE: 10. NOTICE OFACTION PULLED TABLED APPROVED t~ DISAPPROVED AMENDED COUNCIL DIRECTIVE DATE: 11. AGENDA BILL NO: 0~ ' o3,28 6. CLEARANCE COMMENTS: 5. IMPACT ON NON-PASSAGE: Construction of the Sewage Pump Station EB-2 2002 Modifications project will bc delayed, and the City will be in violation of its Federal Court order. 6. IMPACT ON STAFFING~ BUDGETS~ FACILITIES~ EQUIPMENT OR OTHER RESOURCES: Staff'mg: No Impacts Budget: The Sewage Pump Station EB-2 2002 Modifications project is funded by a combination of a Public Works Trust Fund loan and a State Revolving Fund loan. The project is included in thc 2002 Budget and is carried over in the proposed 2003 Budget. Facilities/Equipment: No Impacts 7. RESEARCH SOURCES City CSO Reduction Plan Update and Federal Consent Decree. ab, Agenda Bills 2002, EB-2 Contract Award, 11-02