1. SUBJECT: FOR AGENDA OF: March 27, 2002
WB-6 Pump Station, Contract Award ORIGINATING DEPT: PW&U Engineering Div.
ORIGINATOR: W. Eugene Sampley, Director
DATE SUBMITTED: March 15, 2002
· CLEARANCES: (comment on back,tt/II/l!~,sa.~l~ ~/ 3. EXHIBITS
Director, Public Works/Utilities.~-.- it - ~ A. Bid Tabulation Form
City Attomey ~ L~.~ Site Map
Council Budget & Finance Commi
Council Operations Committee
MAYOR k~-~_ [?/..~ ~ COUNCIL PRES1DENT ~ ~,'~~,
4. SUMI~kRY STATEMENT AND REQUIREMENT FOR COUNCIL ACTION:
Bids were opened for the WB-6 Pump Station project on March 1, 2002. There were six bids received for this
project. Stan Palmer Construction was the lowest responsive bidder with a bid of $1,534,190 (including sales tax.)
The Engineer's estimate for the project is $1,833,279. This project is funded in part by an EPA Grant. The EPA
requires that they approve the low bidder prior to contract award. EPA approval is anticipated by April 5, 2002.
The requested action before the City Council is approval of the contract with Stan Palmer Construction contingent
upon EPA approval.
5. RECOMMENDATION:
The City Council approve award of the WB-6 Pump Station project to Stan Palmer Construction contingent upon
EPA Approval, for the amount of $1,534,190 (including sales tax) and authorize the Mayor to execute the same.
9. RESPONSIBLE OFFICIAL: City Engineer
ENFORCEMENT OFFICIAL: N/A
EXPIRATION DATE:
REVIEW DATE:
10. NOTICE OF ACTION
PULLED TABLED APPROVED ~'""/ DISAPPROVED AMENDED
COUNCIL DIRECTIVE ~~5 f~ ~]~ ¢~ DATE:
11. AGENDA BILL NO: 0o~ -
6. CLEARANCE COMMENTS:
5. IMPACT ON NON-PASSAGE:
The City of Bremerton will not compete the Callow Priority 3 CSO separation by December 31, 2002 as
required by Federal Court order.
6. IMPACT ON STAFFING~ BUDGETS~ FACILITIES~ EQUIPMENT OR OTHER RESOURCES:
Staffing: No Impacts
Budget: The Callow Priority 3 - WB-6 Pump Station Project is funded by a Public Works Trust Fund
loan and EPA grant funding. The project is included in the 2002 budget.
Facilities/Equipment: No Impacts
7. RESEARCH SOURCES