HomeMy WebLinkAbout09/01/99 AGENDA CITY COUNCIL MEETING
and
MONTHLY STUDY SESSION
AGENDA
SEPTEMBER 1, 1999
· CALL TO ORDER: 5:30 P.M.
· CLAIMS/CHECK REGISTERS
Please note that due to the Study Session format of the remainder of this meeting,
there will be no "Council Member Reports"; "Mayor's Report"; "'Legislative Report";
"Public Recognition" or "New Business" items. However, this is an OPEN meeting,
and members of the public are encouraged to attend...
· STUDY SESSION (Please note that times listed are approximate...)
5:30 - 6:00 P.M. (1)
6:00 - 6:30 (2)
6:30 - 7:00 (3)
7:00- 7:30 (4)
Kitsap County Mitigation Plan - Phyllis Mann,
Director of Emergency Management
CSO Reduction Program Updates- Gene
Sampley, Director of Public Works
Construction Projects Update- Randy Witt, City
Engineer
Downtown Redevelopment Implementation- Mayor
Lynn Horton
· ADJOURNMENT OF MEETING
KZTSAP COUNTY
WASHINGTON
D, EPARTtifENT
OF
EII, fERGENCY
tI,IANAGEMENT
Multi-Hazard Mitigation Plan
July .~999
SECTION ONE
Introduction
KITSAP COUNTY MULTI-HAZARD MITIGATION PLAN
Table of Contents
EXECUTIVE SUMMARY .............................................................................................. 4
SECTION ONE: Introduction
I. Definition of Hazard Miligalicm ............................................................................ $
II. Purpose of Plan ................................................................................................. 5
III. Planning Process ............................................................................................... 7
-)
IV. Legal Authority .................................................................................................... 10
SECTION 'i'WO: Process
I. IGlsap County Hazard Vulnerability Analysis .................................................. 11
II Hazard Mitigation Process for Kitsap County ................................................... 11
KITSAP COUNTY DISASTER RECOVERY PLAN
Table of Contents
Summary of Documentation
Materials Record
Labor Record
Emergency Management
Recovery Task Force Checklist
Dos & Don'ts of Damage Assessment
Disaster Assistance Table
Donations Management Diagram
DSR Process Table
Public Assistance Application Chart
Categories of Work
Public Assistance Damage Survey Checklist
Health & Safety
Cleaners & Disinfectants
Restoring Flooded Wells & Cisterns
Septic Tank Failures
Well Volume Estimation
Public Works
Contract for Debris Removal Checklist
Building Inspection
The 50% Rule
Participating in Damage Assessment Diagram
Planning & Community Development
Public Information
Day-to-Day PlO Emergency Information System
DOs & DON'Ts in Dealing With the Media
FC2 Addendum 8
FC2 Addendum 9
FC2 Addendum 10
FC3
FC3 Addendum 1
FC3 Addendum 2
FC3 Addendum 3
FC3 Addendum 4
FC3 Addendum 6
FC3 Addendum 7'
FC3 Addendum 8
FC4
FC4 Addendum 1
FC4 Addendum 2
FC4 Addendum 3
FC4 Addendum 4
FC5
FC5 Addendum 1
FC6
FC6 Addendum 1
FC6 Addendum 2
FC7
FC8
FC8 Addendum 1
FC8 Addendum 2
Table of Contents Page 2
CSO Reduction Plan
Status Update for City Council
September 1, 1999
1) Background
2) Litigation Status
Funding
a) Ecology (FY2000)
i) Callow Priority 3 & 5 Design ($575,000 SRF Loan),
ii) CSO Reduction Plan Update ($191,250 CCWF Grant)
iii) East Bremerton CSO Facilities Plan ($245,000 SRF Loan)
iv) Cooperative Approach to CSO Separation ($150,000 CCWF Grant)
b) PWTF-($7,000,000 FY2000/2001)
i) Callow Priority 3 & 5 Construction ($4,195,800 Loan)
ii) East Bremerton CSO Construction ($2,804,200 Loan)
iii) Applying for East Bremerton CSO Design
c) Federal (?)
i) Seeking direct appropriation of $9,000,000 over 2 years.
(1) $500,000 - FY2000
(2) Balance - FY2001
4)
CSO Reduction Plan and Facilities Plan
a) Purpose of Plan Update
i) Regulatory requirement
ii) Include Facilities Plan (Engineering Report)
b) Consultant- HDR
c) Schedule - 1/2000 approval for Facilities Plan
5) CSO Reduction Projects
a) Work Performed by City Staff
i) Public Education
ii) Flow Optimization
(1) Slip flow- Citywide
(2) Eliminate Overflow 1797 in Callow Basin (25,000,000 gal/yr)
(3) Olympic College storm separation
(4) Bremerton High School storm separation
(5) Other
iii) Construction Projects
b) Competitively Bid Design/Construction Projects
i) Anderson Cove- HDR/Casne/City design
(1) Bid CW-2 September 14 and sewer/storm main improvements
September 22. Request expedited procedure for award.
ii) Callow Priority 3 & 5 - Montgomery Watson design
(1) Contract construction by year-end 2000
iii) Pine Road - HDR/City design
(1) Construct 2000.
(2) Remaining East Bremerton basins begin construction 2000.
c) Other
i) Elimination of OF-15 in PSNS
(1) Constructed storm on First Street into BTC for mutual benefit
(a) Storm treatment - Vortechnic sediment filter in BTC
PUBLIC WORKS AND UTILITIES
3027 Olympus Drive * Bremerton, WA 98310-4799 * (360) 478-5270 * FAX (360) 478-5398
Engineering Division
MEMORANDUM
TO:
FROM:
DATE:
SUB J:
Lynn S. Horton, Mayor
W. Eugene Sampley
Kathleen Cahall
Bob Tulp
Wayne Hamilton
Janet Martelle
John Poppe
Bill McKinney
Phil Berry
Paul Lucas
Gloria Agas
Lynn Price
Engineering Division Staff (Route)
Randy Wit~/~~'4
AMUogn~ Sh~ y27p'r loj9e9c9t S~
Enclosed is the monthly status report for your review. This will be presented at the
study session on September 1, 1999.
RW/ab
Attachment
PUBLIC WORKS AND UTILITIES
ENGINEERING DIVISION
MONTHLY STATUS REPORT
PRESENTED TO THE
CITY COUNCIL ON
SEPTEMBER 1, 1999
RANDY WITT, CITY ENGINEER
BTC PROJECT UPDATE
RANDY WITT, CITY ENGINEER
PUBLIC WORKS PROJECTS UPDATE
JEFF SHEA, SENIOR ENGINEER
UTILITY PROJECTS UPDATE
TOM KNUCKEY, SENIOR ENGINEER
SR304 TRANSPORTATION IMPROVEMENT PROJECT
LYNN PRICE, PROJECT MANAGER
SPECIAL PROJECTS UPDATE
DAN MILLER, PROJECT MANAGER
BTC PROJECT
MONTHLY UPDATE TO CITY COUNCIL
SEPTEMBER 1, 1999
Upland work continues to proceed on the ferry terminal building. Structural steel for the
terminal was set and 735 cubic yards of concrete slabbing material were placed in the last
three weeks. Underground utility construction work is proceeding concurrently.
Construction of the new ferry terminal floats is proceeding for delivery in the fish "window",
when over-water construction is allowed.
The ferry terminal holding area is in its smallest configuration.
Change over of traffic in the ferry terminal area is smoothing out. The intersection of
Burwell Street and Pacific Avenue has been problematic at periods when the ferry terminal
overflows back up to that area. City staff is working with the BTC project partners to
address traffic management in that area.
RW:ab
99277
Randy Witt, P.E., City Engineer
BTC Project/Monthly Update to City Council
September 1, 1999
Page 1
PUBLIC WORKS PROJECT UPDATE
MONTHLY REPORT
AUGUST 1999
WERNER ROAD CORRIDOR/WEST HILLS COMMERCIAL IMPROVEMENTS
Design continues on the stormwater, traffic signal and roadway plans. Designs are
approximately 65 percent complete. Details addressing wall locations, traffic signal layout,
etc. are proceeding.
Right-of-Way acquisition occurs on Kean Boulevard (formerly Rogers Street) properties;
settlement is anticipated in the near future with US West. Other property owners are
obtaining their own appraisals, or in negotiation.
WSDOT is hesitant to allow the City to use the berm area for a detention basin. Design is
proceeding with the assumption that we will not obtain the use of the area, but will provide
for future connection to a detention pond at this site.
CALLOW CSO, PRIORITIES THREE AND FIVE
Montgomery/Watson Engineering was selected as the consultant to submit a proposal for
this work. The consultant submitted a first draft proposal. That draft has been reviewed by
City staff and discussed with the consultant. The consultant is preparing a second draft
proposal for further consideration. Staff anticipates an agreement being presented to the
City Council for this work within the next month.
BURWELL HILL CLIMB
· This work has been sent to the Street Department for construction. Construction is
anticipated to be completed in September 1999.
1999 CURB CUT PROGRAM
· City crews are constructing curb cuts in the vicinity of Olympic College/Bremerton High
School.
1999 TRAFFIC CALMING PROGRAM
· Lyle Avenue has been pre-leveled in preparation for overlaying and installation of speed
humps.
99278
Jeff Shea, Senior Engineer
August 1999
Page #1
ENGINEERING DIVISION
UTILITY PROJECT UPDATE
AUGUST 1999
MISCELLANEOUS WATER PROJECTS
· Final comments are being incorporated into the plans and specifications for the Quarry
Avenue Pump Station. Advertisement is anticipated in the coming weeks.
CALLOW AVENUE PRIORITY 2 CSO SEPARATION
Priority 2
· Construction is complete. Project closeout activities are proceeding.
W650 ZONE IMPROVEMENTS
· The City received 60% design documents for the pump station on July 21~t. Staff is
reviewing, and will provide comments for incorporation into the final design.
ANDERSON COVE CSO
Four projects to be completed by the City are currently in design, and will be constructed
when design is complete, including; storm sewer construction on Wycoff north of 21 st Street,
modifications to the overflow structure and associated piping at pump station CW-1, and
modifications to the overflow structures No. OF-10, and OF-11.
Design of upgrades to Pump Station CW-2 is complete, and will advertise the week of
August BOth, with the bid opening scheduled for September 15th. Design of sanitary and
storm sewers on Snyder Avenue and Ohio Street are nearly complete, with the bid opening
scheduled for September 22nd.
CSO REDUCTION PLAN UPDATE
The proposed scope of work and budget has been received from the consultant for this
project, and is currently being reviewed by staff. Submittal of the project for Council
approval is anticipated in the coming weeks.
City forces have completed smoke testing of sewers in East Bremerton, and will complete
dye testing of East Bremerton in the coming weeks. This information will be used by the
Consultant to identify required capital improvements in the basins.
MULTIBASIN CSO PROJECT
We were recently notified that a project titled "Multibasin CSO Reduction Project" has been
recommended by the Public Works Board for funding from the 2000 Public Works Trust
Fund Construction Loan program. Legislative approval of the loan is schedule for May of
2000. The value of the loan is $2,804,200, and will fund Design of improvements to the Pine
Road Basin, and will fund construction of improvements to the Pine Road, Tracyton Beach,
East Park, and Trenton Avenue Basins.
Monthly Utility Project Update -~.-
SR304 TRANSPORTATION IMPROVEMENT PROJECT
MONTHLY REPORT
August, 99
FUNDING
· No new activity.
BURWELL STREET IMPROVEMENTS
(Montgomery Avenue to Pacific Avenue)
· Work is complete except for the contractor's requirement to maintain the landscaping for a year
after plant establishment..
ACCESS AND DESIGN HEARINGS
· The State Attorney General's office is in the process of resolving the appeal to the "Findings
and Order".
RIGHT OF WAY ACQUISITION
(As of July 21, 1999)
· Of the 73 properties within the early acquisition area between Porter Street and First Street:
>' 71 properties have either been acquired or we have "possession and use orders" on the
properties.
~' Documents approving the donation of Naval property for the project are expected by
early September.
~' "Possession and use" of the former Unocal property is also expected by early
September.
· Of the remaining (12) partial take properties outside of the early acquisition area, nine
properties have been acquired. Possession and Use agreements are still being negotiated with
the owners of the 7/11 and Midas Muffler properties. The minor acquisition at Rainier Auto
site is expected to close by the middle of September.
STRUCTURE DISPOSAL
· City crews will clean up the properties that are being burned as part of the fire training
exercises.
Four houses have been moved by Orca Construction. The other four houses are scheduled to be
moved by September 12th.
The contractor for the Asbestos Removal No. 4 contract has begun asbestos abatement on 8
structures. Work should be completed by the middle of September.
Seventeen structures remain to be removed within the Gateway Improvement Phase. A
demolition contract to remove 4 of the larger structures is scheduled for bid opening on
September 13th. Two additional structures will be moved under a new building move contract.
City crews are scheduled to remove 11 structures in October and November.
SR304 Transportation Improvement Project - 1-
PUBLIC OUTREACH
· The summer edition of the Gateway News was mailed out in July. Additional copies are
available at Public Works Engineering.
ENVIRONMENTAL CLEANUP
· A contract is being prepared to cleanup minor soil contamination on several properties within
the Gateway Improvement phase. The contract will be advertized for bid in early September.
LANDSCAPE COMMITTEE
· No new activity.
GATEWAY IMPROVEMENTS
(Porter Street to Montgomery Avenue)
The consultant has submitted a 95% complete set of plans and specifications for review. It is
anticipated that comments will be returned to the consultant on September 10th. This phase of
the roadway improvement could go out for bid in mid October if there are no delays either due
to right of way acquisition or complying with the endangered species act.
Project File: COMM/PR/3.2
Lynn Price Project Manager
SR304 Transportation Improvement Project -2-
PUBLIC WORKS & UTILITIES
PROJECT UPDATE
AUGUST 1999
EVERGREEN PARK --- PHASE I RENOVATION
Project substantial completion on Monday, August 16th. Presently, the Final
Punchlist items are being completed as final acceptance including the
installation ofhydroseeding and sod.
The project closeout proceedings are underway while the Parks & Recreation
Department is proceeding with additional site amenities towards their re-
dedication ceremony scheduled for September 11 t~.
Note: Parks & Recreation Department established Phase I Re-Dedication Day
for Saturday, September 11 . The Parks & Recreation Department is the
organizer of this event.
EVERGREEN PARK --- PHASE II REMEDIATION
· Acquisition of the Lofthus property is being completed.
· The Agreed Order With Ecology will be before the City Council September
8th.
Reviewed Parametrix, Inc.'s draft scope of work, draft budget estimate, and
proposed schedule; and discussed revisions that will either be incorporated or
changed as to the scope of work, estimate, and schedule sequence towards
finalizing a Professional Services Agreement.
The Phase II proposed schedule indicates demolition of structures this fall and
an early Summer 2000 bid date for remediation with the objective to complete
park construction by December 2000.
MANETTE BALLFIELD RENOVATION
· The Grading, Sub-Drainage and Erosion Control Plan is presently under
review for permit compliance/approval.
· The technical specifications are presently 98% complete and awaiting
comments from the aforementioned compliance review.