HomeMy WebLinkAbout10/04/00 AGENDA CITY COUNCIL MEETING AGENDA
OCTOBER 4, 2000
1. PRE-COUNCIL STUDY SESSION: 5:00 - 5:30 P.M.
A. General Council Business
2. CALL TO ORDER: 5:30 P.M.
A. Pledge of Allegiance
B. Invocation
3. CONSENT AGENDA
There are no Consent Agenda items this week.
4. CLAIMS/CHECK REGISTERS
5. COUNCIL MEMBER REPORTS
6. MAYOR'.S REPORT,.
7. LEGISLATIVE REPORT
8. PUBLIC RECOGNITION - (Comments limited to 3-minutes) ~
9. NEW BUSINESS
A. Bid Award for Pine Road CSO Reduction Facility Storage Basin (#AB00-223) i
10. RESOLUTIONS
A. Resolution No. 2778, Initiating Annexation Procedures for Port Blakely Sub-Area (#AB00- 3
224)
11. ADJOURNMENT OF MEETING
COUNCIL WILL ADJOURN TO THE COUNCIL CONFERENCE ROOM IMMEDIATELY FOLLOWING
THE REGULAR MEETING TONIGHT FOR THE "MONTHLY STUDY SESSION"...
AGENDA BILL
BREMERTON CITY COUNCIL
1. SUBJECT: PINE ROAD CSO REDUCTION FOR AGENDA OF: October 4, 2000
FACILITY STORAGE BASIN - BID AWARD. ORIGINATING DEPT: PW&U Engineering Div.
ORIGINATOR: John Poppe, Wastewater M~..,~
DATE SUBMITiT. I): September 28, 2000
2. CLEARANCES: (comment on back i~e~a~ 3. EXItIRITS
Director, Public Works/Utilities-- ~../~4,a,~2~ _ A. Bid Tabulation.
City Attorney
City Treasurer
Purchasing Agent
Council Budget & Finance Committee
Council Operations Committee
4. SUMMARY' STATEMENT AND REQUIREMENT FOR COUNCIL ACTION:
Bids were opened for the Pine Road CSO Reduction Facility Storage Basin contract on September 29, 2000. This
contract provides for the construction of a 100,000 gallon CSO storage facility and piping. The contract work
includes labor, materials, equipment, and support services as defined in the project bid documents. 3 bids for
this ro'ect were received. STAN PALMER CONSTRUCT I ON was the lowest responsive bidder with a
bid oP[ 'j $329,252.60 i ~ee~~~ f-0~r ~ee p--r~-oje~ is $ 250,000. The action before the City
Council is approval of award of the bid with STAN PALMER CONSTRUCTION , in the amount of
$329,252.60 _, including applicable taxes.
8. RECOMMENDATION:
Move to approve award of the bid with STAN PALMIER CONSTRUCT I ON ., in the amount of
$329,252.60 , including applicable taxes, for the Pine Road CSO Reduction Facility Storage Basin
contract and authorize the Mayor to execute the same.
9. RESPONSIBLE OFFICIAL: City Engineer
ENFORCEMENT OFFICIAL: N/A
EXPIRATION DATE:
REVIEW DATE:
10. NOTICE OF ACTION
PULLED TABLED APPROVED DISAPPROVED AMENDED __
COUNCIL DIRECTIVE DATE:
11. AGENDA BILL NO:
2. CLEARANCE COMMENTS:
5. IMPACT ON NON-PASSAGE:
1. Legal action(s) may result if construction of the storage facility is not completed by January I, 2001.
2. Violation of the PSA Consent Decree and CSO Agreements.
6. IMPACT ON STAFFING, BUDGETS, FACILITIES., EQUIPMENT OR OTHER RESOURCES:
Staffing: Additional operation and maintenance.
Budget;. This project is funded through Public Works Trust Funds and is included in the 2000 Budget.
Facilities/Equipment:
7. RESEARCH SOURCES
CrTY OF BREMERTON
BID TABULATION
DATE OPENED: ~l ~h 10~ TIM E OPEN ED: _c~_~'_C~D~O RECORDED
~D
~D
~DDER RECD ITEM 1 ITEM 2 ITEM 3 ITEM 4 ITEM 5 NET DID TAX TOTAL
AGENDA BILL
BREMERTON CITY COUNCIL
1. SUBJECT: Resolution #2778 FOR AGENDA OF: October 4, 2000
Initiating annexation procedures ORIGINATING DEPT: Economic Devel.
for Port Blakely Sub-Area ORIGINATOR: Warren Olsen
DATE SUBMITTED: September 29, 2000
2. CLEARANCES: (comment on back 3. EXHIBITS:
if~ecgssary~ Resolution ~0, ~
~_.~~?~~ Notice of Intention-City Council
City Attorney ~ overview Chart
Summary of Process
Letter of Intent - Port Blakely
Consistent with the s~-area plan and the three party agreement Port Blakely has initiated
action to annex the area to the city. The steps are as follows:
· Port Blakely provides a letter requesting the City to begin annexation proceedings (see
attached letter dated September 20, 2000).
· The City Council meets with Port Blakely. (This evening's meeting accomplishes this.)
· The City Council passes the proposed resolution that will
1) Acknowledge receipt of the letter.
2) Accept proposed annexation.
3) Accept previous s~ area plan as the comprehensive plan for purpose of
annexation.
4) Determine Port Blakely's obligation for indebtedness.
5) Authorize circulation of formal petition for annexation.
6) Provide Notice of Intent to annex to Boundary Review Board (BRB).
~-7~ Direct staff to provid~ nctict for Public Hearing ~nM first rea~ng
~rdinancc on October I$.
· This action will effectively start the clock on a 45 day review period for the Boundary
Review Board when they have confirmed accuracy of information.
8. RECOMMENDATION:
1. I move to waive the provision of Rule 4 of the Bremerton City Council Rules &
Procedures requiring the proposed resolution on initiation of annexation procedures of Port
Blakely be presented to the Operations Committee and Fiscal & Budget Committee.
2. I move to pass Resolution #2778 accepting the proposed geographic area for
annexation and initiating annexation procedures for Port Blakely Sub-Area.
9. RESPONSIBLE OFFICIAL: Economic Devel.
ENFORCEMENT OFFICIAL: Economic Devel.
EXPIRATION DATE:
REVIEW DATE:
10. NOTICE OF ACTION
PULLED TABLED APPROVED DISAPPROVE~_~~D
COUNCIL DIRECTIVE: DATE:
11. AGENDA BILL NO: 0~-
2. CLEARANCE COMMENTS (cont.):
4. SUMMARY STATEMENT (cont.):
5. IMPACT ON NON-PASSAGE:
Annexation of Port Blakely will not commence.
6. IMPACT ON STAFFING, BUDGETS, FACILITIES, EQUIPMENT OR OTHER RESOURCES
N/A
7. RESEARCH SOURCES:
RESOLUTION NO. 2778
A RESOLUTION OF THE CITY OF BREMERTON, WASHINGTON,
ACCEPTING THE PROPOSED GEOGRAPHIC AREA FOR
ANNEXATION AND INITIATING ANNEXATION PROCEDURES
FOR PORT BLAKELY SUB-AREA.
WHEREAS, the City received a request dated September 20, 2000 (Attachment
C) from Port Blakely Tree Farms as the 100% owner of land to commence annexation
proceedings for the Port Blakely Sub-Area, and,
WHEREAS, the City previously adopted the Port Blakely Sub-Area Plan and
Three-Party Agreement pursuant to Ordinance No. 4722 which both provide for
annexation of the Sub-Area, and
WHEREAS, the City conducted the meeting with the proponent within the 60-day
period as required under the direct petition method under RCW 35.13.125, NOW,
THEREFORE
BE IT RESOLVED BY THE BREMERTON CITY COUNCIL THAT
1. As required by RCW 35.13.125, the City accepts the geographic area
proposed for the annexation as set forth in the legal description (Attachment B) and map
(Attachment A)attached to this Resolution.
2. As provided in RCW 35.13.125, the City has determined to
simultaneously adopt a comprehensive plan and zoning for the property at the time the
City takes action on the formal annexation ordinance. The Port Blakely Sub-Area Plan
previously approved by the City in Ordinance No. 4722 constitutes a comprehensive plan
for purposes of the annexation statute under RCW 35.13.177.
3. As provided in RCW 35.13.125, Port Blakely will assume its
proportionate share of City indebtedness upon annexation and will be assessed and taxed
at the same rate and on the same basis as other similar property in the City for then-
outstanding indebtedness.
4. Port Blakely is authorized to submit an Annexation Petition to the City for
annexation of the Sub-Area property.
5. City Council will immediately submit to the Kitsap County Boundary
Review Board a Notice of Intention to Annex (Attachment D) in the form required by the
BRB.
6. Staff is directed to give notice and schedule public heatings as follows on
a proposed annexation ordinance for the Port Blakely Sub-Area: first reading on
October 18, 2000, and second reading on October 25, 2000.
PASSED by the City Council on this ~ day of ,2000.
Carol Arends, Council President
Attachments:
Map of Annexation Area (A)
Legal Description of Annexation Area (B)
Port Blakely notice of intent dated September 20, 2000 (C)
Notice of Intention to Annex (D)
2
Parametrix. Inc.
8
7
19.i 20
FtGURE07
og/27/oo -- - Port Blokely £oundory Item 3
Section line
L~o--1 ~ Proposed Oevetopment Legal Description Exhibit
O' 1200' Boundary Port Blakely
1"=1200' Topo~.ropny /rom 'Walker and Associates Joint Planning Area
'7
ITEM 3
LEGAL DESCRIPTION
PORT BLAKELY JOINT PLANNING AREA
That portion of Sections 7, 18 and 19 of Township 24 North, Range 1 East of the
Willamette Meridian in Kitsap County, Washington, described as a whole as
follows:
Beginning at the section corner common to Sections 17, 18, 19 & 20 of said
Township and Range; thence along the east line of said Section 18, North 02033'
36" East 2650.40 feet to the east 1/4 section corner of said Section 18; thence
continuing along said east line of said Section 18, North 02013, 37" East 2665.51
feet to the section corner common to Sections 7, 8, 17 & 18 of said Township and
Range; thence along the east line of said Section 7, North 03014' 29" East 273.70
feet; thence South 49006' 36" West 394.86 feet; thence South 22° 15' 57' West
435.82 feet; thence South 51 °04' 39' West 573.87 feet; thence South 72021' 49"
West 281.90 feet to the beginning of a 113 foot radius curve to the right; thence
northwesterly along said curve an arc distance of 212.28 feet through a central
angle of 107°38' 11"; thence North 208.41 feet to the beginning of a 80 foot
radius curve to the left; thence northwesterly along said curve an arc distance of
159.10 feet through a central angle of 113°56' 42"; thence South 66003' 19" West
372.14 feet; thence South 24°07' 12" West 254.43 feet; thence South 38 °38' 11"
West 566.66 feet; thence South 05005' 55" West 1897.32 feet; thence South
12050' 21" West 833.49 feet; thence South 07048' 19" West 495.35 feet; thence
South 46057' 31" West 323.73 feet; thence South 33030' 41" West 410.75 feet;
thence South 17°32' 08" West 860.92 feet; thence South 07042' 01" West
2094.94 feet to the beginning of a 599.00 foot radius curve to the left; thence
southeasterly along said curve an arc distance of 1356.06 feet through a central
angle of 129042, 36"; thence North 57059' 25" East 911.61 feet; thence North
61 °35' 44" East 692.67 feet to the beginning of a 1239.00 foot radius curve to the
left; thence northeasterly along said curve an arc distance of 946.35 feet through
a central angle of 43 °45' 45"; thence North 17°49' 59" East 1763.31 feet to the
point of beginning.
1325 Fourth Ave., 10th Floor
Seattle, Washington 98101-2524
a PORT BLAKELY TREE FARMS, L.P. ph:(206}624-5810
naglng Land and Timber Sfnce 1864 fax:(206)624-9745
September 20, 2000
Bremerton City Council
239 Fourth Street
Bremerton, WA 98337
The Honorable Lynn Horton
239 Fourth Street
Bremerton, WA 98337
RE: Notice of Intent to Commence Annexation Proceedings on Port Blakely Property
Dear City Council and Mayor Horton:
Port Blakely appreciates the City's approval of the Sub-Area Plan and 3-Party
Agreement for Port Blakely's 440-acre property. As provided in the 3-Party Agreement, Port
Blakely hereby delivers its notice of Intent to commence annexation proceedings for the
Property by the petition method under RCW 35.13.125. A legal description and map of the
property are attached for reference ("Property"). Port Blakely owns 100% of the proposed
annexation area.
Under the annexation statute, the City Council is to set a date for a meeting with Port
Blakely to make certain statutory determinations. We request the date be at your next city
Council hearing. Although the statute allows 60 days for the meeting, we would like to
proceed promptly to implement the Plan and begin the next level of analysis. You are very
familiar with the proposed area and project based on the extensive hearings and meetings of
the Plan.
At the meeting, the statute requires 3 matters be addressed. First, the City must
determine whether it will accept, reject, or geographically modify the proposed annexation
area. The area has already been determined in the approved Plan as the UGA area.
Second, the City must determine if a simultaneous adoption of a comprehensive plan
is to be completed. Again, this was part of the approved Plan. The City's Ordinance which
adopted the Plan expressly stated it constitutes a comprehensive plan for purposes of the
annexation statute, RCW 35.13.177 as well as a sub-area plan under the GMA.
September 20, 2000
Page 2
Third, the City must determine whether Port Blakely's Property must assume a
portion of the City's existing indebtedness. Port Blakely is willing to assume its
proportionate share of indebtedness upon annexation and be assessed and taxed at the same
rate and on same basis as other similar property in the city for then-outstanding indebtedness.
If the City Council at the October 4, 2000 meeting approves circulation of the formal
annexation petition, then Port Blakely as the 100% owner of the Property is prepared to
submit its annexation petition for the Property, with final annexation conditioned upon
completion of the following necessary steps: (1) City would send a Notice of Intention with
the Boundary Review Board promptly after the meeting on October 4 which approves the
circulation of the petition; and (2) mutual approval by the City Council and Port Blakely of a
Development Agreement under RCW 36.70B. 170 et seq. and applying the new MXD zoning
to the Property consistent with the uses and development standards in the approved Sub-Area
Plan and 3-Party Agreement.
We look forward to working with the City to complete these steps and conclude an
annexation.
Respectfully submitted,
Port Blakely Tree Farms, (Limited
Partnership), a Washington limited
Partnership
By: ~'.,~"-z:~
4hn L. Adams
Attachments:
Legal Description of Port Blakely Property
Map of Port Blakely Property
CC: Warren Olsen
LEGAL DESCRIPTION
PORT BLAKELY JOINT PLANNING AREA
That portion of Sections 7, 18 and 19 of Township 24 North, Range 1 East of the
Willamette Meddian in Kitsap County, Washington, described as a whole as
follows:
Beginning at the section comer common to Sections 17, 18, 19 & 20 of said
Township and Range; thence along the east line of said Section 18, North 02°33'
36" East 2650.40 feet to the east 1/4 section comer of said Section 18; thence
continuing along said east line of said Section-18, North 02°13' 37" East 2665.51
feet to the section comer common to Sections 7, 8, 17 & 18 of said Township and
Range; thence along the east line of said Section 7, North 03° 14' 29" East 273.70
feet; thence South 49006. 36" West 394.86 feet; thence South 22°15' 57' West
435.82 feet; thence South 51 °04' 39' West 573.87 feet; thence South 72021' 49"
West 281.90 feet to the beginning of a 113 foot radius curve to the dght; thence
northwesterly along said curve an arc distance of 212.28 feet through a central
angle of 107038' 11"; thence North 208.41 feet to the beginning of a 80 foot
radius curve to the left; thence northwesterly along said curve an arc distance of
159.10 feet through a central angle of 113o56. 42"; thence South 66003' 19" West
372.14 feet; thence South 24007' 12" West 254.43 feet; thence South 38038' 11"
West 566.66 feet; thence South 05°05' 55" West 1897.32 feet; thence South
12°50. 21" West 833.49 feet; thence South 07o48. 19" west 495.35 feet; ther~ce
South 46057' 31" West 323.73 feet; thence South 33030. 41" West 410.75 feet;
thence South 17032' 08" West 860.92 feet; thence South 07042. 01" West
2094.94 feet to the beginning of a 599.00 foot radius curve to the left; thence
southeasterly along said curve an arc distance of 1356.06 feet through a central
angle of 129042' 36"; thence North 57059. 25" East 911.61 feet; thence North
61 °35' 44" East 692.67 feet to the beginning of a 1239.00 foot radius curve to the
left; thence northeasterly along said curve an arc distance of 946.35 feet through
a central angle of 43045' 45"; thence North 17°49. 59" East 1763.31 feet to the
point of beginning.
Parametrix. Inc.
FILE: FIGURE07
o^~ 09/20/00 Port Blokely Boundary
Section line Legal Description Exhibit
[--I [--I ~ Proposed Development Port alakely
o s---e0' 12o0' Boundary Joint Planning Area
1 "-- 1200' Topography from Wotker end Associates
239 4th Street · Bremerton. Washington 98337 o ~3§0) 478-5280 · FAX {360} 478-525I o citycouncil@ci.bremerton.wa.us
NOTICE OF INTENTION
OF BREMERTON ANNEXATION
October 5, 2000
Kitsap County Boundary Review Board
Kitsap County Courthouse, MS - 35A
614 Division Street
Port Orchard, Washington 98366
As required by RCW 36.93, a Notice of Intention is hereby given by: CITY OF BREMERTON
As required by local rule of the Board, we are submitting the following information, attached
hereto as part of this NOTICE OF INTENTION, to assist you in your consideration of this
proposed action. The items submitted are numbered in accordance with the listing below:
NOTICE OF INTENTION
1. A Description of the Nature of the Proposed Action, Including a Citation of the
Statutory Provision Under Which the Action Is Authorized.
The City of Bremerton intends to change it boundaries by annexing 440 acres of
unincorporated Kitsap County, known as the "Port Blakely Sub-Area," by the petition
method pursuant to RCW 35.13.125-160. This area has been established by Kitsap
County in its GMA Comprehensive Plan as an Urban Growth Area consistent with RCW
36.70A. 110, and consequently the area is eligible for annexation under RCW 35.13.005.
2. A Brief Statement Regarding the General Background of and the Reasons for
Seeking the Proposed Action.
Kitsap County's 1998 Comprehensive Plan designated the "Port Biakely Sub-Area" for
potential UGA expansion. Since then, the City of Bremerton and Kitsap County have
implemented this designation through a series of actions: (1) a Memorandum of
Agreement and Interlocal Agreement dated 8-24-98; (2) concurrent adoption of the Port
Blakely Sub-Area Plan ("Sub-Area Plan"); and (3) concurrent approval of a Three-Party-
Equal Opportunity Employer
Kitsap County Boundary Review Board
September 29, 2000
Page 2
Agreement. The Sub-Area Plan and Three-Party Agreement were adopted by the City on
September 20, 2000, and by the County on September 11, 2000. All of these actions are
based on the annexation of this Sub-Area into the City of Bremerton. See e.g. "The
[K/map] County will support the annexation in accordance with this [three-party]
Agreement and the [Port Blakely] Sub-Area Plan." Sec. 2 of the Three-Parry Agreement.
The Three-Party Agreement requires Port Blakely to submit its annexation petition to the
City within 30 days after adoption of the Sub-Area Plan.
Additional reasons for seeking the proposed annexation are set forth in the Sub-Area
Plan, which amends the Comprehensive Plans of Kitsap County and the City. This
annexation area has been designated for economic development through industrial,
commercial and other employment-generating uses, in a mixed-use concept, along with
supporting housing. The annexation is consistent with the Growth Management Act in
allow4ng the City to be the primary service provider for utilities and services.
3. Legal Description. The legal description of the annexation area is attached as Item 3.
4. Assessor Map. The Kitsap County Assessor map showing the annexation area and the
current City, boundaries is attached as Item 4.
5. Vicinit?' Map. The vicinity map with the annexation area and significant geographic
features with a ½ mile surrounding area is attached as Item 5.
6. City Boundary. Map. A map showing the current City of Bremerton boundaries is
attached as Item 6.
7. A Review of Factors Stated in RCW 36.93.170 as They Affect the Proposed Action.
7.1 Population and Territor3~.
(a) Population; Territory; and Population Density. The 440-acre Sub-
Area Plan is located west of the Kitsap Lake community along the north
boundary of the City. The Sub-Area Plan allocates 900 single-family units
(or up to 1.200 units of multifamily), which corresponds with a potential
mixed-use housing population ranging from 2.238 to 2,724 people (i. e..
900 to 1.200 units multiplied bv 2.27 people/household per the housing
element of the City of Bremerton Comprehensive Plan). This mixed-use
housing population is a reallocation of a portion of the City's existing
population of 20,000 people. See Sec. l. 4 of Plan. Specifically, the
reallocated population is reassigned from the City's downtown central
business district and other business districts which were originally
designated for mixed-use housing as "targeted development areas." As
described in the Sub-Area Plan and appendices, this mixed-use housing
Kitsap County Boundary. Review Board
September 29, 2000
Page 3
has not occurred in the original targeted development areas and
consequently is being reallocated.
(b) Land Area and Land Uses. The 440-acre Sub-Area Plan property
currently is used for forestry, but has now been placed within the UGA
established bv the County. The annexation area is proposed for mixed-use
development including the following: 2.25 million square feet of
industrial-commercial uses; 100,000 square feet of retail uses and up to
900 single-family equivalent houses (or 1,200 multi-family units at a
conversion ratio of .75). Approximately 140 acres of the total 440-acre
total area will remain open space and undeveloped due to critical areas,
buffers and mitigation. See Sec. 1.2, 1.3, 3 and 4.1 of Sub-Area Plan for
further description of land area and land uses.
(c) Comprehensive Plans and Zoning. Both the County and City
Comprehensive Plans designate this as an UGA area for industrial and
mixed-use development under the Growth Management Act (RCW
36.70A). See Sec. 1.5 and 1.6 of the Sub-Area Plan. Upon annexation.
zoning for the property will be "Mixed-Use District" under the City's
zoning code.
(d) Service Agreements. The Sub-Area Plan contains a Capital Facilities
element specifying the service providers and costs allocations or
responsibilities for the same. The City will provide the following primary
basic services: water, sewer, stormwater, solid waste, parks and
recreation, law enforcement, fire and emergency ser~4ces. The County
will provide certain administrative facilities such as courthouses and
regional facilities. See Sec. 4.6 and 5 or the Sub-Area Plan. Other
utilities will be provided by the service providers currently serving the
area: Puget Sound Energy for electricity; Cascade Natural Gas for natural
gas; and U.S. West for telephone and telecommunications. See Sec. 6 of
the Sub-Area Plan. No service agreements under Chap. 36.115 RCW nor
39.34 are applicable.
(e) Interlocal Agreements. The Three-Party Agreement between the City.
County and Port Blakely addresses annexation of the Sub-Area and
constitutes the Interlocal Agreement called for in the County's 1998
Comprehensive Plan Policies UGA 6 through 13. See Sec. 2 of Three-
Party Agra. Further, the City and County entered into a Memorandum of
Agreement and Intertocal Agreement dated 8-24-98 which governed
development of the Sub-Area Plan.
Kitsap County Boundary Review Board
September 29, 2000
Page 4
(0 Per Capita Assessed Valuation. The assessed valuation for the Sub-Area
Plan property is $68,200 based on the forest land classification under
Chap. 84.33 RCW; currently there are no residents in the Sub-Area.
(g) Topography, Natural Boundaries, Drainage Basins and Proximity. to
Other Populated Areas. The Sub-Area Plan describes the general site
physical parameters. The site is generally level. Based upon preliminary.
analysis, the steepest slopes are approximately 15% and there are no
identified areas of instability or seismic activity. Approximately 300 acres
of the total 440 acres are unconstrained by critical areas. The remaining
approximately 140 acres will be set aside to meet critical area regulations
for streams, wetlands and buffers and for open space and consistent uses.
The soils on the site var5' in permeability. Drainage from the site flows
primarily to Kitsap Lake, while approximately 2% to 3% of the site flows
to Dickerson Creek. Both of these bodies of water feed into Chico Creek
which is the home of an important salmon run. The Sub-Area Plan
addresses mitigation measures for drainage and fish habitat and the scope
for further environmental analysis. See Sec. 4.2 of the Sub-Area Pla~. The
site is generally separated by major topographic features: Dickerson Creek
on the west and north; steep slopes on the north, east. south and northwest:
and the BPA power line corridor and railroad corridor on the east. The
residential area around Kitsap Lake has been built out. The only
proximate residential neighborhood surrounds Kitsap Lake. with houses
located approximately 300' (from the north end) to 900' (from the middle
and south end) as measured from the eastern boundary of the Port Blakely
Sub-Area boundary. See Fig. 2 and 3 of the Sub-Area Plan.
(h) No Prime Agricultural Soils and Uses. The site does not contain prime
agricultural soils or uses. The site is used for timber harvesting. The Sub-
Area was not designated by the County as appropriate for forest lands of
long-term commercial significance under the GMA.
(i) Likelihood of Significant Growth in the Area and Adjacent Areas.
The Sub-Area Plan itself is anticipated to develop as mixed use as
described above in the land use discussion (Subsection 7.1 (Io) above). The
adjacent County unincorporated areas are not expected to change in the
next 10 years since they are not outside of the urban growth areas
designated under the GMA. The site is generally separated by major
topographic features: Dickerson Creek on the west and north; steep slopes
on the north, east. south and northwest: and the BPA power line corridor
and railroad corridor on the east. The residential area around Kitsap Lake
has been built out. Consequently, the impact of development on
unincorporated areas is anticipated to stay directly within the annexation
Kitsap County Boundary Review Board
September 29, 2000
Page 5
area. See Fig. 3 and 6 of the Sub-Area Plan. The adjacent incorporated
areas already within the City may be developed consistent with the City's
Comprehensive Plan and its ability to provide services.
O) Community Facility Location. The community facilities currently
provided by the City of Bremerton are set forth generally in the City's
Comprehensive Plan. The Sub-Area Plan for Port Blakely describes the
contribution of rights of way or funds for various capital facilities as
development conditions. Existing Fire Station No. 2 can serve this site
and meet LOS for fire and emergency services. See Sec. 5 of the Sub-Area
Plan. There likely will be some utility facilities on-site such as reservoirs.
The Sub-Area Plan did not identify any major additional community
facilities on-site, but this will be further evaluated during the master
planning. Contribution of fair share funding will be made as set forth in
the Capital Facilities element of the Sub-Area Plan for off-site facilities.
See same. The Three-Party Agreement contains a master transportation
agreement between the City, County and property owner for transportation
studies and specific access improvements. See Sec. 3 of Three-Par~' Agra
7.2 Municipal Sen'ices; Prospects From Other Sources; Probable Future Needs.
(a) Need for Municipal Services. The Sub-Area Plan sets forth the required
municipal services and facilities for the annexed area. See Sec. 5 and 6 of
the Sub-Area Plan. The City has issued certificates of sewer and water
availability consistent with existing City regulations. The City will
provide other services as noted in Subsection 7.1 (d) above, including fire
and emergency services, law enforcement, parks, stormwater, water and
sewer. The Capital Facilities element of the Sub-Area Plan sets forth the
LOS standards for development within the annexation area consistent with
existing codes and development regulations. See same. The Bremerton
School District will provide school service.
(b) Effect of Codes, Regulations on Existing Uses. The existing uses in the
Sub-Area are governed by County codes and state regulations for forest
operations. Upon annexation, the Sub-Area will be governed by the City's
codes and regulations, along with special environmental controls set forth
in the Sub-Area Plan and Three-Party Agreement. See Sec. 4.2 q/'the Sub-
Area Plan and Sec. 5 and 6 qf the Three Par~ Agra.
(c) Present Cost and Adequacy of Services and Controls in the Area. The
Capital Facilities element of the Sub-Area Plan sets forth the existing
adequacy of services for the existing uses. and identifies those services
and funding sources to provide expansion of services and facilities. The
Kitsap County Boundary Review' Board
September 29, 2000
Page 6
cost of existing municipal services is minimal to the site due to its forestry
use. Regulatory' controls by the count5, and state for existing uses are
adequate.
(d) Probable Effect and Cost and Adequacy of Services and Controls in
Area and Adjacent Area. The Sub-Area Plan identifies the estimated
costs for extending services and controls. The Capital Facilities element
shows adequate levels of service, costs and funding sources and related
information for infrastructure to serve the annexation area. See Sec. $ of
the Sub-Area Plan. The Three-Party Agreement contains a master
transportation agreement, with joint funding of $2.4 million by each parts.~,
individual funding responsibilities of Port Blakely, and phasing and
analysis for transportation needs. See Sec. 3 of the Three-Party Agm. The
transportation improvements will benefit adjacent areas. No growth is
expected in adjacent unincorporated areas requiring additional services.
(e) Prospects of Governmental Services from Other Sources; Probable
Future Needs for such Services and Controls. The City does not
require services from other sources to serve the site, as reflected in the
Capital Facilities of the Sub-Area Plan. See Sec. 5 of the Sub-Area Plan.
Transportation improvements may seek state or federal funds, grants or
other sources as a result of the studies under the master transportation
plan. See Sec. 3 ef the Three-ParO' Agra. Improvements to County roads
will be identified and contributions made as a result of the master plan to
be prepared as required under the Three-Party Agreement.
(f) Probable Effect of Proposal on Cost and Adequacy of Services. The
Capital Facilities element sets forth the costs as estimated currently for
services to the Sub-.ha-ea. All services are shown as adequate currently or
with concurrency, phasing and contributions as development occurs at the
site, See Sec. 5 of the Sub-Area Plan. The City has issued certificates of
sewer and water availability consistent with existing City regulations. See
also answers to Subsections 7.2(a) and (d) above.
(g) Effect on Finances. Debt Structure and Contractual Obligations of
Governmental Units. No significant impacts are expected on finances.
debt structure or contractual obligations of governments. The land owner
is obligated to pay its fair share of expanding services and facilities and is
obligated to pay for the environmental and planning review required. See
Sec. 5 of the Sub-Area Plan: Sec. 3. 4 and 5 qf the Three-Party Agra. The
compensating tax to be paid by the owner when the land is removed from
the forest land taxation will be paid the County. Sec. 10 c?fthe Three-ParO'
Agm. The approved Three-Party Agreement does commit the Citx' and
Kitsap County Boundary Review Board
September 29, 2000
Page 7
County to contribute up to $2.4 million as pan of the joint master
transportation plan on the terms set forth therein. Sec. 3 of the Three-Party
Agra. Future transportation funding decisions will be made by the City
and County respectively. Same.
7.3 Effect on Adjacent Areas, Mutual Economic and Social Interests and Local
Government Structure of the County. The Sub-Area Plan calls for
environmental and aesthetic mitigation to avoid any significant adverse effects on
adjacent areas. The Sub-Area Plan sets forth a series of performance standards
and a detailed scope for further environmental review as part of the master plan
which is required before development of the annexation property. The only
proximate residential neighborhood surrounds Kitsap Lake, with houses located
approximately 300' (from the north end) to 900' (from the middle and south end)
as measured from the eastern boundary of the Port Blakely Sub-Area boundary.
See Fig. 2 and 3 of the Sub-Area Plan.
The annexation area is undertaken expressly to advance mutual economic
interests of the City and County. The area was identified as necessary to expand
Kitsap CounU"s overall industrial and employment base. The annexation is not
expected to have any adverse affect on social interests nor on the structure of local
government within the County. The City will be the primary provider of services
consistent with the Growth Management Act and the allocation of responsibility
provided in the Plan and the Three-Party Agreement.
8. A Review of the Effect of the Proposed Action Upon the Objectives Set Forth for the
Boundary Review Board in RCW 36.93.180.
8.1 Preservation of Natural Neighborhoods and Communities. The annexation
area is adjacent to the existing City boundary. Once developed under the MXD
zoning and Sub-Area Plan, the site will create natural neighborhoods and
communities. The project will meet the mixed-use criteria in the subarea plan and
will create a strong sense of community. It also will contain mitigation to reduce
off-site impacts on the Kitsap Lake residences, which are located at least 300 to
900' from the boundaDr of the site and situated on the opposite side of the BPA
corridor, the railroad corridor and West Kitsap Lake Road.
8.2 Use of Physical Boundaries. The 440 acres was selected in large part using
physical boundaries and topography. The site is relatively flat. The City and
County previously moved the annexation boundaries to eliminate all but 2% to
3% on the land from the Dickerson Creek drainage basin as a mitigation measure
for salmon. The annexation area also was configured so that maximum relatively
fiat developable areas were included and critical areas or other constraints were
minimized. The site is generally separated by major topographic features:
Kitsap County Boundary Review Board
September 29, 2000
Page 8
Dickerson Creek on the west and north; steep slopes on the north, east. south and
northwest; and the BPA power line corridor and railroad corridor on the east.
8.3 Creation and Preservation of Logical Services Areas. The annexation area will
be a logical extension of the City's service areas as reflected in the Capital
Facilities element of the Sub-Area Plan. As a mixed-use area, services will be
efficient and numerous facilities can serve "double" by being available for both
residential, commercial and related uses.
8.4 Prevention of Abnormal, Irregular Boundaries. The annexation area does not
have abnormal, irregular boundaries. The shape is dictated in part by topography
and physical features and in part by a location of the existing road system and
existing railroad corridor.
8.5 Discouragement of Multiple Incorporations. The annexation will not result in
a new incorporation of small cities. Bremerton is an existing major urban area
and annexation would be consistent with the discouragement of small cities.
8.6 Dissolution of Inactive Special Purpose Districts. The proposal does not
dissolve anv inactive special purpose district.
8.7 Adjustment of Impractical Boundaries. The proposal does not affect or adjust
impractical boundaries.
8.8 Incorporation or Annexation of Urban Character Areas. This area was
designated under the Growth Management Act as appropriate for annexation and
urban development. The size and approximate location of this UGA was
reviewed and upheld by the Growth Hearings Board based upon the CounD"s
study and need for additional industrial lands and employment base. [GMHB
Final Decision7 and Order, dated 2/8/99; Compliance Order. dated ] 0/] 1/99. ]
The GMA defines "characterized by urban growth" as both land having urban
growth on it or land "located in relationship to an area with urban growth on it as
to be appropriate for urban growth." RCW 36. 70A.030(] 7). The County's UGA
designation and the GMHB affirmation establishes the appropriateness of this
property for urban development.
8.9 Protection of Agricultural and Rural Lands Designated for Long-Term
Agricultural or Resource Use. This site has not been designated for long-term
agricultural or forestry, use under the GMA. Although this land historically has
been used for forestry, the County reviewed and expressly determined not to
designate this land as long-term forestDr land. See GMHB Compliance Order.
dated 10/] 1/99
Kitsap County Boundary. Review Board
September 29, 2000
Page 9
9. Filing Fee. The $50 filing fee is enclosed.
10. The Statement of the Current Status of Environmental Review of the Proposed
Action Including Complete Documentation of the Environmental Review to Date.
The City and County have adopted phased environmental review for the Sub-Area Plan.
Three-Party Agreement, and related Comprehensive Plan and zoning actions. These
include the proposed annexation of the Sub-Area to the City as covered in this Notice of
Intent. The County and City adopted the Sub-Area Plan and related Comprehensive Plan
amendments, and Three-Party Agreement, based upon the revised Determination of
Significance and Adoption of Environmental Documents. See City and County SE?A
determinations attached. The adopted prior documents include the final EIS issued
August 23, 1994 for the County's Comprehensive Plan; the Final SEIS issued
December 2, 1996; and Addendums issued March 12, 1998 and April 11, 1998. The
adequacy of these environmental documents have been upheld by the GMHB. The next
SEPA phase, a project-level master plan EIS, is required under the Three-Party
Agreement. See Sec. 4 of the Three-Party Agm. The Sub-Area Plan itself contains an
extensive scope for that project-level EIS. See Vol. I. Appen. 1 of the Sub-Area Plan.
The project-level EIS will be required before any development of the site. See Sec. 4 of
the Three-Par~ Agra
The total acres of the property involved in this proposed action is 440 acres, and the total
assessed valuation of said property is $68,200 based on the forest land classification under Chap.
84.33 RCW
Kitsap County Boundary Review Board
September 29, 2000
Page 10
Notice: Process and other communication regarding this proposed action should be directed to
the initiator of this proposal as follows:
Paula Johnston, City of Bremerton
239 4~ Street
Bremerton, Washington 98337
Phone: (360) 478-5311
Fax: (360) 478-5200
Respectfully submitted,
City Council
CITY OF BREMERTON
By
Carol Arends, President
Attachment s:
Copy of City Resolution Accepting Annexation Area
Copy of Port Blakely 100% Annexation Petition
Legal Description (Item 3)
Assessor Map (Item 4)
Vicinity Map (Item 5)
City Boundary Map (Item 6)
SEPA Determination of City and County.
Port Blakely Sub-Area Plan
Three-Party Agreement
CITY PROCESSING STEPS FOR PORT BLAKELY ANNEXATION
Approval/Action Description Estimated Date
Port Blakely's letter requesting Port Blakely submitted to City Sept. 20, 2000
annexation triggering 60-day meeting
City Council meeting and City Council holds meeting within October 4, 2000
Resolution commencing annexation 60 days to accept notice, decide on
process, bonded indebtedness and authorize
circulation of annexation petition
and send BRB notices
PB's Annexation petition Port Blakely as the 100% property October 4, 2000
owner submits its annexation
petition with legal description and
plat or survey of annexation
boundaries.
City sends to BRB a Notice of City City Council files with BRB a October 5, 2000
Intent to Annex the Port Blakely Notice of Intent to Annex on BRB
Sub-Area. form.
County letter to BRB supporting Optional, but City may request By Nov. 1, 2000
annexation Kitsap County to send a letter of
support for annexation--which the
County has agreed to support in Sec.
2 of the 3-Party Agrn
Notice of public hearings for City staff gives required 1 O-day By October 8,
(1) Planning Commission and (2) notice of public hearings on the 2000
Council I annexation ordinance.
City
Planning Commission hearing on The MXD zoning classification October 17, 2000
MXD zoning and initial (added to code in Ord. 4723 on
Development Agreement Sept. 20, 2000 is proposed for the
Port Blakely property, along with an
initial Development Agreement.
C:\WINDOWS\TEM P\GWVIEWERXANNEX CHART_I .DOC
Seattle/9.29.00
Approval/Action t Description Estimated Date
City Council hearing on annexation The annexation ordinance would I 1st Reading:
and ordinance adopting concurrent accomplish these actions.I Oct. 18, 2000
actions:
2nd Reading:
Oct. 25, 2000
1. Annexation; Add area to City boundaries
2. Zoning for annexed Apply the new MXD zone to the
property; Property.
3. Port Blakely Initial Adopt the initial, preliminary
Development Agreement Development Agm as Type III
decision, which will (a) incorporate
by reference the Project elements
and performance standards from the
Sub-Area Plan and (b) set out the
next steps for environment review
and processing the Master Plan. At
the time the initial Dev. Agra is
adopted, many of the environmental
and other development standards
will be deferred until the ElS and
Master Plan are completed.
i
BRB approval of annexation 45 day automatic approval if BRB November 20 (it'
jurisdiction is not invoked. Notice of Intent is
I filed at least on
October 5)
2
C:\WINDOWS\TEMP\GWVIEWER~ANNEX CHART_I .DOC
Seattle/9.29.00
September 27, 2000
To: Bremerton City Council
From: Warren Olson
Re: Annexation of West Kitsap Lake (Port Blakely)
Summary of action/process for October 4, 2000
Consistent with the sub-area plan and the three party agreement Port Blakely has initiated
action to annex the area to the city.
The steps are as follows:
· Port Blakely provides a letter requesting the City to begin annexation proceedings
(see attached letter dated September 20, 2000.
· The City Council meets with Port Blakely. (This evenings meeting accomplishes
this)
· The City Council passes the proposed resolution that will
1) Acknowledge receipt of the letter.
2) Accept proposed annexation.
3) Accept previous sub area plan as the comprehensive plan for purpose of
annexation.
4) Determine Port Blakely's obligation for indebtedness.
5) Authorize Circulation of formal petition for annexation.
6) Provide Notice of Intent to annex to Boundary Review Board (BRB).
7) Direct staffto provide notice for Public Hearing and first reading of
annexation ordinance on October 18.
· This action will effectively start the clock on a 45 day review period for the
Boundary Review Board when they have confirmed accuracy of information.
Subsequently an ordinance for annexation will be proposed. This action can be taken
simultaneously with the Boundary Review Boards Review period.
· A ten day notice period is required because it is a land use action.
· The Council can hold the hearing and first reading on October 18, 2000.
· The second reading and adoption can occur on October 25, pending final
completion of Boundary Review.
An initial development ag, reement will be created during this time that will reflect work
already completed in the sub-area plan and three party agreement. The development
agreement will need to be reviewed by the planning commission pr/or to adoption.
The next steps required will be the Environmental hnpact Statement (ELS) and Mas~er
Plan.
To: Council Members
From: Council Member David Farr ~
Date: October 3, 2000
Re: Parking Lot Barriers
Recently I had problems with parking in the back parking lot (like running over
the parking barriers!) due to the current configuration of spaces and barriers.
The barriers are difficult to see and the location of the barriers makes it difficult to
drive out of the lot.
Please let me know if you would support the removal of the concrete barriers to
make parking in those parking spots easier.